Edinburg Completes $1.44M Chapin Pond Pump Project

The city finished the pump system at Chapin Pond on schedule and within budget to add stormwater capacity.

Updated on Nov. 17, 2026 in Emergency Response

Wide view of a South Texas stormwater pond with squat steel pump housings on a concrete pad, a concrete outflow channel running down a grassy embankment, and mesquite scrub at the edges.
The City of Edinburg completed a $1.44 million pump project at Chapin Pond on schedule and within budget, adding 69 million gallons of stormwater capacity after a 2018 flood. AI Illustration. Upload story photo >

Live Poll

Do you trust your local government to handle flood prevention well?

Edinburg has completed a $1.44 million pump project at Chapin Pond, adding room for 69 million additional gallons of stormwater. The project was finished on schedule and within budget and passed testing.

Why it matters

The project was designed to reduce flood risk following a 2018 flood event in Edinburg. The new pumps make roughly 15 feet of the pond's depth usable for storage, giving the city more capacity during heavy rain.

The city reports $1.44 million in total project cost and 69 million additional gallons of stormwater capacity, with a $1 million state disaster recovery grant covering part of the cost. How much flood protection the pumps deliver under heavy rainfall has not been quantified in the reporting.

The players

City of Edinburg

Edinburg is a city in Hidalgo County in the Rio Grande Valley of South Texas, and it administers the municipal stormwater infrastructure involved in the project.

Texas Division of Emergency Management

The state agency that administers disaster recovery grants, which funded $1 million of the Chapin Pond project.

The details

Before the upgrade, water reached Chapin Pond through a gravity-fed pipe. The new pumps push water into the pond and make unused storage space usable. The pumps can run on diesel if electricity goes out, and construction began in August 2025.

Timeline

  1. 2018: Major flood event prompted the project's flood-risk goal.

  2. August 2025: Construction on the Chapin Pond pump project began.

  3. November 17, 2026: Pump project completion was reported.

  4. In the coming months: Edinburg plans to begin building another detention pond.

Seasonal Patterns

The Chapin Pond upgrade is a direct response to the 2018 Edinburg flood, which exposed the limits of the city's gravity-fed stormwater system. The added 69 million gallons of capacity marks a shift from passive drainage toward active pumping for flood control.

Residents in the Edinburg area should follow city stormwater and flood advisories during heavy rain, as the pumps add capacity but do not eliminate flood risk. Property owners near Chapin Pond can monitor city announcements for updates on the planned detention pond.

The takeaway

Upgrades like the Chapin Pond pumps add stormwater capacity, but their flood protection depends on rainfall, so residents should keep following local flood guidance.

What happens next

Edinburg plans to begin building another detention pond in the coming months.