Denton Weighs 90-Day Data Center Moratorium

City Council takes a final vote on pausing new data center development while water, wastewater and electric capacity are reviewed.

Updated on Nov. 28, 2026 in Data Centers

Bold flat-color editorial illustration of a modular data center building with cooling units and overhead transmission poles across open prairie.
The Denton City Council takes a final vote December 1 on a 90-day moratorium halting new data center applications while water, wastewater and electric capacity are reviewed. AI Illustration. Upload story photo >

Live Poll

Should your city pause new data centers until water and power limits are addressed?

The Denton City Council is scheduled to hold a final vote on December 1, 2026, on a 90-day moratorium that would halt new data center applications across the city and its utility service areas. The proposal requires at least three-fourths of the full council to pass.

Why it matters

Denton's water production, wastewater treatment and electric transmission capacity are each reported to be strained by peak demand, and the city does not currently have a process for prioritizing data center connection requests. The moratorium is intended to protect the health, safety and general welfare of residents until needed regulations are established.

Denton Municipal Electric reports about 75 megawatts of available transmission-level capacity, while Core Scientific has a peak power agreement of 391 megawatts and the WAHA/Qumulus AI project covers 20 megawatts. The city has not stated how these commitments would be reconciled with its remaining capacity.

The players

Core Scientific

Core Scientific is a data center company whose peak power agreement with Denton's utility totals 391 megawatts.

WAHA/Qumulus AI

WAHA/Qumulus AI is a data center project in Denton with a reported capacity of 20 megawatts.

The details

Changes approved in October require a specific-use permit for data centers, increase the residential setback from 100 feet to 300 feet, and prohibit evaporative cooling. Under the proposed ordinance, applications already protected under state vested-rights law would not be halted, and the moratorium would end when the city adopts needed regulations or after 90 days, whichever comes first.

Timeline

  1. October 2026: Denton approved tightened data center rules.

  2. November 2026: Texas regulators resumed data center permit processing after Gov. Greg Abbott's temporary pause ended.

  3. December 1, 2026: Denton City Council holds its final vote on the moratorium.

  4. March 1, 2027: The initial moratorium is scheduled to expire under the city's current work plan.

Roadmap

Denton's proposal follows Texas state regulators resuming data center permit processing after Gov. Greg Abbott's temporary pause ended in November 2026. It adds a local hold layered on top of that statewide resumption, as cities across Texas weigh how to manage the strain of rapid data center growth on their utilities.

If the moratorium passes, residents would see a pause on new data center approvals across Denton's water, wastewater and electric service areas until the city adopts regulations or 90 days pass. Projects already protected under state vested-rights law would continue regardless.

The takeaway

Denton's utility figures show that peak demand already exceeds some system capacities, so the outcome of the December vote will shape how the city balances growth with infrastructure limits. Residents interested in the issue can follow the council's final decision on December 1.

What happens next

The Denton City Council is scheduled to hold its final vote on the moratorium on December 1, 2026, and the initial moratorium is set to expire March 1, 2027 under the city's current work plan.

Further reading

Explore more on Data Centers coverage for Denton.

Source note: This article includes information reported by Chron.