Denton to Start Poor House Run Stream Restoration
Town and ShoreRivers begin a two-phase project to restore eroded streambanks and replace a Fifth Street culvert.
Updated on Nov. 20, 2026 in Utilities

The Town of Denton and ShoreRivers are beginning a two-phase restoration of Poor House Run, a stream that carries stormwater from much of the town's developed area. Construction is expected to start the week after Thanksgiving 2026 and continue through the end of the year, weather permitting.
Why it matters
Stormwater volume and force have eroded the stream's banks and damaged nearby infrastructure, including flooding on Fifth Street. Combining stream restoration with culvert replacement aims to repair infrastructure while restoring the stream's natural function for Denton residents.
The first phase covers approximately 625 feet of Poor House Run from Fifth Street downstream, while the second phase could close Fifth Street for four to five weeks in the worst case. Final timing remains subject to weather and site conditions.
The players
ShoreRivers
ShoreRivers is a Chesapeake Bay-area nonprofit that works on watershed restoration and water-quality projects across the Eastern Shore.
Town of Denton
The Town of Denton is the municipal government of Denton, Maryland, responsible for local infrastructure such as roads, culverts and stormwater systems.
The details
Crews will restore two eroded branches of Poor House Run and replace the existing culvert under Fifth Street on the northwest side of the Legion Road intersection. No road closures are planned during the stream work, and crews will use the Choptank Community Health parking lot to support it.
Timeline
Week of Thanksgiving 2026: Equipment arrives and crews begin work.
Week after Thanksgiving 2026: Stream restoration construction is expected to start.
End of 2026: Phase one stream work is expected to finish, weather permitting.
February and March 2027: Second-phase culvert replacement under Fifth Street is scheduled.
Utilities Context
The project is funded in whole or in part by the Maryland Whole Watershed Program, which supports restoration of waterways feeding the Chesapeake Bay. Poor House Run flows into the Choptank River, linking this local stormwater fix to the wider Bay cleanup effort.
Drivers on Fifth Street should expect possible closures of up to four to five weeks during the second phase in early 2027. Residents near Poor House Run may notice construction activity through the end of 2026, though no road closures are planned during the first phase.
The takeaway
Stormwater management projects like this one often combine stream repair with road infrastructure work, so residents should plan for temporary detours during the early 2027 Fifth Street closure window.
What happens next
Construction is expected to begin the week after Thanksgiving 2026, with the second-phase Fifth Street culvert replacement scheduled for February and March 2027.
Further reading
Explore more local infrastructure coverage in Denton Utilities.
Source note: This article includes information reported by The Star Democrat.






