CapMetro Board Weighs $51M Plaza Saltillo Expansion
The contract would fund a station expansion at East 5th and Comal streets, with construction projected to run into 2029.
Updated on Nov. 16, 2026 in Industry

Live Poll
Should Austin spend $51 million expanding the Plaza Saltillo rail station?
The CapMetro board votes Monday at noon on a proposed contract of just over $51 million to expand the Plaza Saltillo commuter rail station. The expansion would add two 280-foot side platforms and double-track the line from Onion Street to Matamoros Street.
Why it matters
The expansion is intended to improve access to commuter rail for an area that continues to grow with commercial and residential development. The contract is funded from CapMetro's capital budget and supported by $18 million in federal RAISE grant money.
The proposed contract includes a $44.5 million base construction amount and a 15% contingency bringing the total to about $51.1 million. CapMetro has already received $18 million in federal RAISE grant funding, and the board has not yet approved the award to Jay-Reese Contractors.
The players
Jay-Reese Contractors
Jay-Reese Contractors is the Austin-area firm that would receive the contract, having previously built the Waterloo Greenway and the Longhorn Dam Wishbone Bridge.
CapMetro
Capital Metropolitan Transportation Authority is the public transit agency serving the Austin area, operating commuter rail and bus service.
The details
The expansion would include enhanced pedestrian safety rail crossings at Navasota, Comal, Onion, Chalmers and Robert T. Martinez streets, along with a bike and pedestrian path from Chicon Street to Pedernales Street. The contract would be awarded to Jay-Reese Contractors, which previously built the Waterloo Greenway and the Longhorn Dam Wishbone Bridge.
Timeline
Monday, November 16, 2026, at noon: CapMetro board vote on the proposed contract.
January 2027: Construction on the expansion would begin.
April 2027: Work on station platforms and track infrastructure would start.
Spring 2029: Construction work would continue into this period.
Industry Dynamics
The project draws on $18 million from the federal RAISE grant program, placing this local commuter rail expansion within a broader pattern of federal discretionary transit funding supporting metropolitan rail upgrades. The contract's contingency structure and multi-year construction schedule follow the typical pattern of capital rail projects in the region.
Riders using the Plaza Saltillo station may see construction activity around East 5th Street and Comal Street beginning in 2027 and continuing into 2029. The expansion is designed to improve commuter rail access for people living and working in the growing surrounding area.
The takeaway
Because the project is funded from CapMetro's capital budget and federal grant money, its progress depends on the board's vote and the schedule of work that follows. Riders and nearby residents should expect multi-year construction near the station.
What happens next
The CapMetro board vote on the contract is scheduled for Monday, November 16, 2026, at noon, with construction on the expansion projected to begin in January 2027.