ERCOT Plans Demand Limits for Texas Computing Sites
Grid operator would cap combined electricity draw for monitored sites, including Riot Platforms' Corsicana bitcoin mine, to reduce outage risk.
Updated on Nov. 29, 2026 in Data Centers

Live Poll
Do you think grid power limits on crypto mining would make your area safer?
The Electric Reliability Council of Texas (ERCOT) plans to activate group limits on electricity demand for monitored computing sites when combined demand reaches roughly 2,500 megawatts. The shared operating ceiling for the group is 2,720 megawatts, and Riot Platforms' Corsicana bitcoin mine is part of the monitored group.
Why it matters
The limits are designed to reduce the risk that multiple computing sites disconnect at the same time after a transmission fault. ERCOT modeled a scenario in which the sudden loss of 3,200 megawatts of demand could push grid frequency to 60.4 cycles per second under certain conditions, increasing the risk that outages could spread.
ERCOT's modeling projected a 3,200-megawatt sudden demand loss during a transmission fault, and the monitored group's September simultaneous draw was 1,615 megawatts against approvals totaling 5,465 megawatts. How ERCOT's modeled risk compares with actual operating conditions after activation has not been reported.
The players
Electric Reliability Council of Texas (ERCOT)
ERCOT is the independent grid operator managing electricity flow for most of Texas, and it oversees reliability and market operations across the state's power system.
Riot Platforms
Riot Platforms is a publicly traded bitcoin mining company that operates large-scale mining facilities, including its Corsicana site in Texas.
The details
ERCOT assigns group shares based on recent consumption, so added computing demand could narrow the remaining capacity before individual sites reach their approved amounts. The limits can be activated for the transmission providers and market schedulers responsible for the sites, constraining how much power Corsicana and other facilities can draw, and Riot's existing Corsicana operations qualify for an exemption from newer requirements to remain connected during voltage and frequency disturbances.
Timeline
January 2026: During Winter Storm Fern, miners reduced demand by an estimated 4,100 megawatts.
September: Monitored group sites reached a simultaneous draw of 1,615 megawatts.
Third quarter: Riot booked about $24.7 million in power credits.
When Riot filed its quarterly report: ERCOT's group-limit plan had not yet been activated.
Big Picture
The plan extends ERCOT's existing reliability framework to cover coordinated computing demand, which can disconnect simultaneously after a transmission fault in ways conventional loads typically do not. It follows the grid's experience during Winter Storm Fern in January 2026, when large flexible loads cut demand sharply to help stabilize the system.
Computing sites in the monitored group could face caps on how much electricity they draw once combined demand passes the threshold, which may limit operating schedules during peak periods. Customers and businesses in Texas depend on the grid's stability, so the limits are aimed at reducing the chance of widespread outages.
The takeaway
Grid reliability in Texas increasingly depends on how large, flexible computing loads are coordinated, not only on how much power is generated. Operators of computing sites should track how their demand compares with group ceilings as ERCOT moves toward activating the limits.
Further reading
For related coverage of how computing facilities draw on regional power systems, see Data Centers on Wisevoter.
Source note: This article includes information reported by TokenPost.