Upper Trinity Water District Wins CMAA Project of the Year

The Lake Ralph Hall Raw Water Pump Station earned the highest overall recognition among CMAA's 2026 award recipients.

Updated on Nov. 23, 2026 in Utilities

Large concrete pump house with tall steel intake pipes rising from a reservoir shoreline under a wide, clear Texas sky.
Upper Trinity Regional Water District received the 2026 Project of the Year Award from the Construction Management Association of America for its Lake Ralph Hall Raw Water Pump Station. AI Illustration. Upload story photo >

Upper Trinity Regional Water District received the 2026 Project of the Year Award from the Construction Management Association of America for its Lake Ralph Hall Raw Water Pump Station, presented October 5 at CMAA's national conference in Denver, Colorado. The project also received a CMAA Project Achievement Award in the Water/Wastewater/Utility category.

Why it matters

The recognition highlights a major capital investment in Texas water infrastructure, a program the district describes as one of the most significant in its history. The facility is designed to initially pump up to 55 million gallons of raw water per day and expand to 80 million gallons per day as future demand grows, supporting regional supply for communities across the state.

The award recognizes a pump station designed to start at 55 million gallons per day and scale to 80 million gallons per day. The source does not specify when the expansion will occur.

The players

Upper Trinity Regional Water District

A regional water utility serving Denton County and surrounding areas in North Texas, responsible for the Lake Ralph Hall raw water program.

Construction Management Association of America

A national professional association for construction management that presents annual project awards recognizing excellence in delivery and collaboration.

Freese and Nichols

A Texas-based engineering firm that served as design and construction management partner on the Lake Ralph Hall Raw Water Pump Station.

Archer Western

A construction company that served as construction manager at risk on the Lake Ralph Hall Raw Water Pump Station project.

The details

The district selected Freese and Nichols as design and construction management partner and Archer Western as construction manager at risk, using a delivery approach that emphasized early coordination, risk management and collaboration. An integrated testing loop allowed the team to test and optimize pump performance before connecting the facility to the larger water delivery system.

Timeline

  1. Planning and permitting for the Lake Ralph Hall program began more than two decades ago.

  2. The CMAA Project of the Year award was presented October 5, 2025, at the national conference in Denver, Colorado.

Utilities Context

The Lake Ralph Hall program is among the most significant capital investments in the history of Upper Trinity Regional Water District. Its staged design, starting at 55 million gallons per day and scaling to 80 million gallons per day, reflects long-range planning for Texas water supply.

Residents served by the district benefit from expanded raw water pumping capacity planned for the future. The facility's integrated testing loop was designed to confirm pump performance before it enters service, supporting reliable delivery to customers.

The takeaway

Large water infrastructure projects are increasingly delivered through collaborative models that emphasize early coordination and performance testing before operation. The Lake Ralph Hall pump station illustrates how staged capacity planning can prepare a regional system for growing demand.