Texas Advances EnCore Energy Uranium Permit
The Texas Commission on Environmental Quality completes its technical review for the Upper Spring Creek uranium project.
Updated on Oct. 27, 2026 in Oil and Gas

Live Poll
Should your community support the expansion of local uranium extraction projects for energy production?
The Texas Commission on Environmental Quality has completed the technical review and public notice phase for the Upper Spring Creek PAA-1 uranium project. This regulatory milestone clears the path for enCore Energy to continue expanding its extraction operations in the Clay West district.
Why it matters
This project is intended to support the company's broader expansion of South Texas uranium extraction activity. By utilizing a satellite ion-exchange plant and production wellfield, the site aims to bolster local production capacity.
The project targets uranium within mineralized sands located 300 to 450 feet below the surface. EnCore Energy maintains a potential annual yellowcake production capacity of 1 million pounds across its operations.
The players
Texas Commission on Environmental Quality
This is the state regulatory agency responsible for overseeing environmental protection and permitting for industrial projects in Texas.
enCore Energy
The company is an operator focused on the extraction and processing of uranium throughout South Texas.
The details
The facility uses in-situ recovery to extract uranium from underground formations. The company then transports the uranium-loaded resin to the Rosita Central Processing Plant for final yellowcake processing.
Timeline
December 2020: EnCore Energy acquired the Upper Spring Creek project from Signal Equities LLC.
May 1, 2026: New Texas notice and hearing procedures took effect.
October 19, 2026: The public comment period for the project closed.
October 27, 2026: The company reported the completion of the technical review and notice.
November 13, 2026: The regulator is expected to issue the final PAA-1 authorization.
Market Landscape
This project represents a broader effort to expand uranium production in Texas as companies scale operations to meet energy sector demand. The move follows the adoption of new state regulatory notice and hearing procedures that now govern how projects move through the approval pipeline.
This expansion could increase regional industrial activity and local employment related to uranium extraction and processing. Residents near the Clay West district may see continued development and regulatory monitoring as the project nears final authorization.
The takeaway
As Texas continues to refine its permitting processes, companies must strictly adhere to the updated public notice and hearing standards established in mid-2026. This case highlights the complexity of balancing large-scale mineral extraction with state-mandated environmental oversight.
What happens next
The Texas Commission on Environmental Quality is expected to issue the final PAA-1 authorization on November 13, 2026. Additionally, enCore Energy anticipates authorization for the PAA-3 Extension by the end of 2026 and approval for PAA-8 in early 2027.
Further reading
Learn more about local industry developments in the Texas Oil and Gas section.