Texas Regulators Remanded Big Hill Power Line Plan
The Public Utility Commission sent the 200-mile transmission project back to administrative law judges for review.
Updated on Oct. 6, 2026 in Utilities

Live Poll
Should utility companies have more authority to build power lines across private land in your area?
On September 9, 2026, the Public Utility Commission remanded the proposal for the 765kV Big Hill transmission line. The decision follows opposition from landowners and concerns regarding project notification failures.
Why it matters
The commission remanded the proposal to re-evaluate the project against federal and state reliability standards and projected congestion cost savings. This move addresses ongoing scrutiny after 1,400 residents were not properly notified about the development.
The proposed Big Hill line, designated as Import Path Two, spans nearly 200 miles with a 765kV capacity. The commission has previously approved Import Path One and Import Path Three.
The players
Public Utility Commission
This is the state agency that regulates electric, telecommunication, and water and sewer utilities in Texas.
Oncor
Oncor is a major regulated electric transmission and distribution service provider in Texas.
LCRA
The Lower Colorado River Authority is a wholesale power provider and water management organization in Texas.
The details
Administrative law judges are now tasked with drafting a supplemental proposal for decision to return to the commission. Landowners have also requested a formal audit of the project, which continues to face significant opposition.
Timeline
August 2026: Landowners spoke against transmission lines at a hearing.
September 9, 2026: The Public Utility Commission chairman remanded the transmission line proposal.
End of September 2026: The original deadline for the commission's decision.
Spring 2027: The upcoming legislative session in Austin will address utility reform.
Market Landscape
The remanded proposal must be measured against federal and state reliability standards, which govern grid performance. The commission sent the plan back specifically to ensure the project meets these established benchmarks for energy delivery.
Residents along the 200-mile proposed route face continued uncertainty regarding land use and infrastructure development. The lack of notification for 1,400 people has prompted calls for greater transparency and oversight in future utility projects.
The takeaway
Large-scale energy infrastructure projects require rigorous adherence to public notification protocols to maintain community trust. Regulatory bodies remain focused on balancing the need for grid reliability against the concerns of private landowners.
What happens next
Administrative law judges will draft a supplemental proposal for decision, followed by a future review by the Public Utility Commission. The Texas Legislature is also expected to address potential utility reform during the session in Austin in the spring of 2027.
Further reading
For more on grid infrastructure projects, visit the Texas Utilities section.
Source note: This article includes information reported by Kwtx.
Live Poll
Should utility companies have more authority to build power lines across private land in your area?










