Texas Regulators Remanded Transmission Line Application
The state utility commission delayed a major power line proposal to address concerns over necessity and landowner impact.
Updated on Sept. 25, 2026 in Utilities

Live Poll
Should regulators approve large-scale transmission projects even if they negatively impact local landowners?
The Public Utility Commission of Texas has remanded a proposal for the 200-mile Bell County East Switch to Big Hill Substation 765-kV Transmission Line Project. Commissioners ordered administrative law judges to further review the necessity of the project and its impact on landowners.
Why it matters
The decision follows a 196-page recommendation for denial from the State Office of Administrative Hearings. Regulators require more data on reliability standards and potential consumer congestion cost savings before moving forward.
The proposed 765-kV transmission line covers a 200-mile span between Bell and Schleicher counties. A previous recommendation for denial of the project spanned 196 pages.
The players
Public Utility Commission of Texas
This is the state agency responsible for regulating electric, telecommunication, and water and sewer utilities in Texas.
Oncor Electric Delivery
This is a regulated electric utility company that provides transmission and distribution services to a large portion of Texas.
Lower Colorado River Authority
This is a conservation and reclamation district that provides energy, water, and community services across Texas.
State Office of Administrative Hearings
This agency provides independent administrative law judges to conduct hearings for state regulatory bodies in Texas.
The details
Oncor Electric Delivery and the Lower Colorado River Authority filed the application in March 2026. The commission has now asked for additional clarification regarding landowner notification procedures and reliability standards.
Timeline
Oncor and LCRA filed the project application in March 2026.
Chairman Gleeson issued the remand memo on September 9, 2026.
The commission voted to remand the proposal on September 11, 2026.
Market Landscape
This project highlights the ongoing tension between large-scale grid expansion and local stakeholder rights in the Texas energy market. The commission's remand follows established procedural requirements set by the Texas Public Utility Regulatory Act.
Residents in Burnet County and along the proposed 200-mile path face ongoing uncertainty regarding land usage. Any eventual approval of the transmission line could impact property rights and local infrastructure development in the region.
The takeaway
The regulatory process prioritizes comprehensive review to ensure that major infrastructure projects meet strict reliability and economic standards. Landowners and stakeholders can participate in the ongoing review process as judges draft the required supplemental proposals.
Further reading
For additional context on local grid expansion, see the Utilities section.
Source note: This article includes information reported by DailyTrib.