Board Weighs DC Blox Data Center Near Nashville Zoo

Zoning appeals over a proposed data center beside the zoo go before the Board of Zoning Appeals on Dec. 3.

Updated on Nov. 27, 2026 in Tech

Photograph of a plain windowless data center building with a metallic facade and rooftop cooling units beside bare autumn trees and a chain-link fence.
DC Blox's proposed data center beside the Nashville Zoo goes before the Board of Zoning Appeals on Dec. 3, as the zoo and Councilmember Courtney Johnston challenge the project. AI Illustration. Upload story photo >

Live Poll

Should new data centers be allowed to be built near public spaces in your city?

Metro Nashville's data center permit moratorium expires Tuesday, and the Board of Zoning Appeals will consider appeals over DC Blox's proposed data center near the Nashville Zoo on Dec. 3. The zoo and Metro Councilmember Courtney Johnston argue Metro mischaracterized the project, while DC Blox contends the Council's new regulations cannot apply to it.

Why it matters

The dispute turns on whether a building permit application filed before the Metro Council's July data center rules and moratorium is governed by the rules in effect at filing. The zoning administrator said no data center rules applied when the application was submitted, a determination that will shape how Nashville regulates facilities near public land.

The building permit application was filed May 29, 2026, before the Council enacted its data center regulations and moratorium in July. The Board of Zoning Appeals has not yet ruled, and appellants' briefs are due Monday.

The players

DC Blox

DC Blox is a data center company seeking approval to build a facility next to the Nashville Zoo.

Metro Nashville

Metro Nashville is the local government that enacted the data center regulations and permit moratorium.

Courtney Johnston

Courtney Johnston is a Metro Nashville councilmember who has appealed the proposed data center project.

Joey Hargis

Joey Hargis is the Metro zoning administrator who determined the application is subject to rules in effect when it was filed.

The details

DC Blox sought approval to build a data center next to the Nashville Zoo. Zoning administrator Joey Hargis wrote on Nov. 10 that he cannot consider the Council's legislation as grounds to review the application, and the appeals from the zoo and Councilmember Johnston will be heard Dec. 3.

Timeline

  1. May 29, 2026: DC Blox submits its building permit application.

  2. July 2026: Metro Council enacts data center regulations and the permit moratorium.

  3. Nov. 10, 2025: Zoning administrator Joey Hargis writes to the board on application rules.

  4. Monday, Dec. 1, 2026: Appellants' briefs are due.

  5. Dec. 3, 2026: Board of Zoning Appeals considers the zoo and Johnston appeals.

Big Picture

The dispute over Metro's July data center regulations and moratorium will determine whether applications filed beforehand are governed by older rules. The Board of Zoning Appeals' ruling on DC Blox's project will set a precedent for how Nashville handles data center proposals near public land.

Nearby residents and zoo visitors will see whether a data center is built beside the zoo, depending on how the appeals are decided. The outcome also determines which Metro rules govern similar projects filed before new regulations take effect.

The takeaway

Permit timing can decide which rules apply to a project, so residents following local zoning fights should check when an application was filed. The Board of Zoning Appeals' Dec. 3 decision will show how Nashville applies its new data center rules.

What happens next

The Board of Zoning Appeals considers the zoo and Johnston appeals over DC Blox's proposed data center on Dec. 3, 2026.

Further reading

For related coverage, see Data Centers in Nashville.

Source note: This article includes information reported by Timesfreepress.