Merrill Lynch Stays, Reshaping Rutherford Renovation
Rutherford County's former Bank of America building renovation is now split into phases, with completion targeted for December 2028.
Updated on Nov. 20, 2026 in City Hall

Live Poll
Do you trust your county government to manage its building projects well?
Tenant Merrill Lynch is remaining in the former Bank of America building in Murfreesboro, Tenn., rather than moving across the street as the seller and attorneys had indicated two weeks before the county closed on the property. The design team redesigned first-floor systems to permanently house the tenant, and the project is now being split into multiple phases.
Why it matters
The change alters how Rutherford County plans to convert the building into government offices, shifting from a single project to a phased approach. Residents and county officials will see the timeline and cost picture reshaped by the tenant's decision to stay.
Merrill Lynch pays Rutherford County $20,000 per month in rent, and its dedicated parking allocation drops from roughly 28 spaces to about 18. The Guaranteed Maximum Price has not yet been presented to the committee, so final costs remain unconfirmed.
The players
Merrill Lynch
A global financial services firm and the tenant occupying the former Bank of America building in Murfreesboro.
Joe Carr
A former Rutherford County mayor whose administration funded only the deconstruction phase of the building project.
The details
Engineers redesigned first-floor mechanical and electrical systems to install a permanent HVAC system for Merrill Lynch instead of temporary systems. Crews will install permanent climate control before starting interior demolition and construction, and the previous administration under former County Mayor Joe Carr had funded only the deconstruction phase.
Timeline
Two weeks before county closing: seller and attorneys notified the design team that Merrill Lynch would stay.
November 19, 2026: Kline delivered a project update to the Property Management Committee.
December 1, 2026: Final construction documents are due.
Early to mid-January 2027: Guaranteed Maximum Price expected to be presented to the committee.
July 2028: Merrill Lynch lease can be renegotiated.
Political Context
The original plan assumed a single renovation project, but the tenant's decision to stay forces the county to phase the work. Opponents on the committee have not publicly addressed whether the phased approach changes the cost-benefit case for the building.
Residents will see county government offices delayed as the project moves through phases ending in December 2028. Parking near the building is also changing, with the tenant's allocation dropping to about 18 spaces.
The takeaway
Phased renovations can absorb unexpected changes like a tenant staying put, but they also stretch timelines and make final costs harder to pin down until the Guaranteed Maximum Price is set.
What happens next
The Guaranteed Maximum Price is expected to be presented to the committee in early to mid-January 2027, and final construction documents are due December 1, 2026.
Further reading
For more local government coverage, see City Hall in Murfreesboro.
Source note: This article includes information reported by WGNSRadio.