Johnson City Began Reassembly of Square Deal Arch

The historic structure has returned to Main Street after a two-year restoration period.

Updated on Oct. 5, 2026 in Openings & Closings

A large steel arch section hangs from a construction crane above a quiet urban street in Johnson City.
Crews have begun reassembling the historic Square Deal Arch on Main Street in Johnson City after a two-year restoration project. AI Illustration. Upload story photo >

Live Poll

In your area, do you believe temporary road detours are worth the long-term historical preservation?

Main Street in Johnson City has closed to traffic as crews begin the reassembly of the historic Square Deal Arch. The monument, originally built by the Endicott Johnson Shoe Company, is returning to the city following a two-year restoration project.

Why it matters

The arch serves as a significant local landmark originally dedicated on Labor Day 1920. Its return restores a prominent piece of the community's industrial history.

The restoration project has lasted two years since the structure was disassembled in October 2024. Crews anticipate the final reassembly phase will be completed in two to three weeks.

The players

Endicott Johnson Shoe Company

This former major footwear manufacturer was responsible for the original construction and dedication of the Square Deal Arch in 1920.

Lupini Construction

This construction firm is managing the reassembly of the steel and concrete structure on Main Street.

The details

Workers have staged cranes and necessary heavy equipment at the Main Street site to handle the steel and concrete components. Lupini Construction has been tasked with the reassembly of the pieces, which are scheduled for delivery on October 6, 2026.

Timeline

  1. The Square Deal Arch was originally dedicated on Labor Day 1920.

  2. The structure was disassembled in October 2024.

  3. Fencing was erected around the project site on October 5, 2026.

  4. Arch pieces are scheduled for delivery on October 6, 2026.

  5. Project completion is expected later in October 2026.

Market Landscape

The reassembly of the Square Deal Arch follows the precedent set by the 1920 dedication of the Square Deal Arch. This project marks a significant effort to preserve local industrial heritage within the broader context of urban infrastructure revitalization.

Local residents and motorists should prepare for continued closures on Main Street while heavy equipment remains on-site. The project will likely restore local landmark access once construction is finished later this month.

The takeaway

The return of the arch highlights the community commitment to maintaining local historic landmarks. Residents should monitor local traffic alerts for updates regarding the reopening of Main Street following the construction window.

What happens next

The final completion of the reassembly project is expected within two or three weeks from October 2026.