Bullhead Trail Reopens After Two-Year Smokies Rehab

Great Smoky Mountains National Park has reopened Bullhead Trail following a two-year rehabilitation project in the Cherokee Orchard area.

Updated on Nov. 25, 2026 in National Parks

Stone steps and a dry-stone retaining wall climb a misty, forested slope through tall hardwood trees under soft overcast light.
Great Smoky Mountains National Park reopened Bullhead Trail on Tuesday after a two-year rehabilitation project that repaired erosion and improved drainage on the approach to Mount Le Conte. AI Illustration. Upload story photo >

Great Smoky Mountains National Park has reopened Bullhead Trail after a two-year rehabilitation project that began in May 2025. The work improved drainage, restored trail conditions, and enhanced visitor safety on the route to Mount Le Conte.

Why it matters

The project addressed erosion and heavy use from visitors and weather on one of several routes to Mount Le Conte. For Tennessee residents and visitors planning hikes in the Smokies, the reopened trail offers safer, more stable footing on a popular approach.

Crews regraded four miles of trail surface on Bullhead Trail. Friends of the Smokies contributed $1.16 million through its Trails Forever endowment, which funds a permanent trail crew, though the extraction does not report total project cost.

The players

Great Smoky Mountains National Park

A national park straddling the Tennessee and North Carolina border, among the most visited units of the National Park System in the United States.

Friends of the Smokies

A nonprofit organization that raises private funds to support the programs and trails of Great Smoky Mountains National Park.

The details

Crews repaired dry-stone retaining walls, added new stone steps, built turnpikes and erosion-control structures, removed tripping hazards such as exposed roots and rocks, widened eroding sections, and pruned overgrown vegetation. The park also rehabilitated Cliff Tops Trail and upper sections of several trails near the summit of Mount Le Conte, including new drainage features and bridges.

Timeline

  1. May 2025: Rehabilitation work on Bullhead Trail began.

  2. Two-year period: The rehabilitation project was completed and the trail reopened.

Season Trajectory

The Bullhead Trail reopening is an example of the permanent trail crew model that the Trails Forever endowment funds in the Smokies. Its rehabilitation work on the approach to Mount Le Conte adds to the park's ongoing effort to manage erosion from heavy visitor use.

Hikers planning to reach Mount Le Conte via Bullhead Trail can expect a regraded surface and new stone steps along its four rehabilitated miles. Visitors should check current park conditions before heading out, since the reopened route now carries the repaired drainage and retaining structures.

The takeaway

Trail rehabilitation funded by a permanent crew can protect popular routes from erosion and visitor wear. Hikers who use these repaired sections help keep them stable for future visitors.

Further reading

For more on the park system, explore National Parks coverage for Tennessee.

Source note: This article includes information reported by The Smoky Mountain News.