The Tennessee Valley Authority disclosed in an SEC filing that a single unnamed data center customer will make aggregate payments under its new tariff.

Updated on Nov. 24, 2026 in Tech

Bold vector editorial illustration of a steel transmission tower on a rolling green valley ridge under a cream sky, with power lines stretching across the frame.
The Tennessee Valley Authority reported $1.7 billion in aggregate payments from an unnamed data center customer under its new tariff, according to a November SEC filing. AI Illustration. Upload story photo >

Live Poll

Do you expect your electricity bills to rise over the next few years?

The Tennessee Valley Authority will receive $1.7 billion in aggregate payments from an unnamed data center customer under its new tariff, according to a Nov. 12 SEC filing. The utility's new data center tariff took effect Oct. 1 and applies to facilities above 5 MW.

Why it matters

The payments show how the tariff is shaping the utility's revenue as it funds a large capital program. Tennessee residents and ratepayers have a direct stake, since TVA warns that continued cost pressures could increase pressure on power rates.

The tariff sets capacity commitment charges at roughly $1.5 million per MW of requested capacity above 5 MW. TVA has not disclosed how many megawatts the unnamed customer has requested.

The players

Tennessee Valley Authority

TVA is a federally owned utility that supplies electricity to most of Tennessee and parts of surrounding states, and it has been expanding generation and nuclear projects.

Mike Skaggs

Skaggs is TVA's chief executive, named permanent CEO by the board on Nov. 10, who has overseen the utility's data center rate changes.

Tom Rice

Rice is TVA's president and chief financial officer, who said the utility is in a strong financial position to execute its $13 billion capital plan.

The details

TVA said the payments come under a cohort-based pricing methodology that may be revised for future customers, with the tariff phasing in through 2029. Existing customers can keep their current rate structures for a period of time. TVA CEO Mike Skaggs said the change to data center rates has supported the utility's investments.

Timeline

  1. August: TVA's board approved 1.5 GW of new natural gas generation, targeted to be online in 2032.

  2. Sept. 30: TVA had spent $463 million on long-lead-time equipment for previously approved projects.

  3. Oct. 1: The new data center tariff took effect.

  4. Nov. 10: TVA's board named Mike Skaggs permanent CEO.

  5. Nov. 12: TVA filed the SEC disclosure of the $1.7 billion in payments.

Roadmap

TVA's data center tariff, which applies to facilities above 5 MW, is one of the mechanisms the utility is using to fund expansion, alongside its approved 1.5 GW of new natural gas generation. The utility's pricing approach is designed so that future data center customers can be grouped into new cohorts with different terms.

Households and businesses served by TVA may see the effects of data center demand reflected in future power rates, since the utility says ongoing supply chain and inflation pressures could raise costs. The tariff phase-in through 2029 means existing customers can keep their current rate structures for a period of time.

The takeaway

Data center demand is now a direct factor in how Tennessee's utility funds its growth, so changes to tariffs and rates can reach everyday ratepayers. Watching how TVA revises its cohort pricing for future customers will show how those costs are shared.

Further reading

For more on how facilities like these are changing power demand, see Data Centers coverage on Wisevoter.

Source note: This article includes information reported by Utility Dive.

Live Poll

Do you expect your electricity bills to rise over the next few years?