TVA Approves 230 MW Power for Korea Zinc Smelter
The Tennessee Valley Authority board approved a power supply for Korea Zinc's Project Crucible integrated smelter in Tennessee.
Updated on Nov. 15, 2026 in Manufacturing

Live Poll
Would you support a large new smelter bringing jobs to your community?
Korea Zinc announced on November 15, 2026 that it has secured a power supply foundation for its integrated smelter in Tennessee after the Tennessee Valley Authority board approved a 230 MW contract for subsidiary Crucible Zinc. The board met on November 10, 2026.
Why it matters
The approval removes a key infrastructure hurdle for a project that Korea Zinc says will produce 12 types of non-ferrous metals, including 11 critical minerals designated by the U.S. government, and semiconductor sulfuric acid. For Tennessee, the project is projected to bring more than 400 new local jobs.
The Tennessee Valley Authority board approved a contracted 230 MW supply, a request that exceeded the 100 MW level requiring board deliberation, for a project with approximately 7.4 billion dollars in planned investment. Pricing terms and the schedule for full power delivery beyond the planned 2029 start were not disclosed.
The players
Korea Zinc
Korea Zinc is a South Korean non-ferrous metal smelting company whose operations include the Ulsan Onsan Smelter, which it has run for about 50 years.
Tennessee Valley Authority
The Tennessee Valley Authority is a federal public utility that supplies electricity to more than 10 million people across seven states in the southeastern United States.
The details
Project Crucible was designated in April 2026 as the first project to use the FAST-41 fast-track permitting system, and its final environmental impact assessment was approved in September 2026. The U.S. Department of War confirmed a 'no significant environmental impact' decision, and Korea Zinc chairman Choi Yun-birm met TVA board chairman Mitch Graves in May 2026 to discuss initial power demand.
Timeline
April 2026: Project Crucible designated for FAST-41 fast-track permitting.
May 2026: Korea Zinc chairman Choi Yun-birm met TVA board chairman Mitch Graves.
September 2026: Final environmental impact assessment approved.
November 10, 2026: TVA board approved the 230 MW power request.
2027: Construction of Project Crucible scheduled to commence.
Industry Dynamics
Project Crucible is the first project designated under the FAST-41 fast-track permitting system, making its progress from environmental approval to a secured power supply an early test of that program. The project's U.S. location and government-designated critical minerals place it within a broader federal push to build domestic non-ferrous metal capacity.
For Tennessee residents, the project is projected to create more than 400 new local jobs once it is operating. The power supply will flow from the Tennessee Valley Authority, the federal utility serving the region, so the project's energy demand will factor into the utility's regional planning.
The takeaway
Large industrial projects depend on secured power long before construction begins, and the Project Crucible approval shows that utility commitments can come years ahead of production. Residents tracking local job growth should watch for the 2027 construction start and the 2029 power delivery date.
What happens next
Construction of Project Crucible is scheduled to commence in 2027, and commercial production of some products starts in 2029.