Sioux Falls Reopens Minnesota Ave Lanes by Winter

Public Works says all five lanes of the $12.2 million Minnesota Avenue rebuild will reopen this winter, with some work pushed to spring.

Updated on Nov. 24, 2026 in Industry

Sioux Falls Reopens Minnesota Ave Lanes by Winter

Sioux Falls Public Works will reopen all five lanes of Minnesota Avenue this winter, though the $12.2 million rebuild between Second and Eighth streets will not finish on schedule. Persistent rain on 40 of 65 days from early September into November disrupted construction.

Why it matters

The delay pushes additional paving and landscaping into spring, extending disruption for drivers and pedestrians along the corridor. It also shows how fall weather can reshape the timeline of major municipal infrastructure projects in Sioux Falls.

The $12.2 million project spans the avenue between Second and Eighth streets, and precipitation fell on 40 of 65 days from early September through the first week of November, according to the city's account. Exact spring closure dates have not been specified.

The players

City of Sioux Falls

The City of Sioux Falls is the South Dakota municipal government that owns and oversees the Minnesota Avenue reconstruction through its Public Works department.

The details

A temporary hard surface is being laid on the southern end of the project to reopen traffic before winter. Existing parking lanes along Minnesota Avenue will be removed, and wider pedestrian paths and colored concrete will separate vehicle lanes from walkways. A 42-inch water transmission line will replace a 36-inch line installed in the 1960s near Eighth Street, a connection that was delayed until the end of November.

Timeline

  1. Early September to first week of November: fall construction season with precipitation on 40 of 65 days.

  2. End of November: water main connection near Eighth Street scheduled for replacement.

  3. This winter: all five lanes of Minnesota Avenue reopen to traffic.

  4. Next spring: lane closures for permanent concrete surfacing, plus medians, lighting and landscaping.

Roadmap

The city had planned to lay permanent roadway surfacing on the Minnesota Avenue rebuild in fall, a timeline that weather and a complicated water main connection have now pushed back. Work that slips into spring, including concrete surfacing and landscaping, follows the same pattern of fall schedules absorbing delays from wet seasons.

Drivers on Minnesota Avenue between Second and Eighth streets should expect all five lanes to reopen this winter, but some lane closures will return in spring. Residents who use the corridor may see delays while concrete surfacing and landscaping are completed.

The takeaway

Fall weather can stall major road projects, so plan for spring disruption on Minnesota Avenue even after lanes reopen. Check local city updates before changing commute routes this winter.

What happens next

Lane closures for permanent concrete surfacing are expected in spring, with medians, lighting and landscaping to follow next spring.