Dakota Gold Projects 171,000 Oz. Annual Output

A prefeasibility study for the Richmond Hill project in South Dakota lowers the mine life to nine years while raising initial capital costs.

Updated on Nov. 24, 2026 in Business

Flat vector editorial illustration of a terraced heap-leach pad in a steep valley beside a crusher tower under a pale sky.
Dakota Gold projects 171,000 ounces of gold a year for nine years at its Richmond Hill mine in South Dakota, but initial capital rises 40% to $538 million. AI Illustration. Upload story photo >

Dakota Gold released a prefeasibility study projecting 171,000 oz. of gold annually for nine years at its Richmond Hill project in South Dakota. Shares fell 8% to $4.02 in New York on Tuesday morning.

Why it matters

The study raises initial capital to $538 million, up 40%, and cuts the mine life from 17 years to nine, while the base-case after-tax net present value rises to $2 billion from $1.6 billion. The updated plan assumes lower gold recovery and remains subject to permits and a construction decision.

The prefeasibility study projects a 5% discount rate, 1.56 million oz. of lifetime payable production (down from 2.6 million), and a $539 million approximate market valuation for the company. Dakota Gold aims to add at least 10% to reserves through higher-recovery breccia drilling before the mid-2027 feasibility study.

The players

Dakota Gold

Dakota Gold is a publicly traded gold exploration and development company whose Richmond Hill project in South Dakota is the subject of the study.

Robert Quartermain

Robert Quartermain is a co-chair of Dakota Gold who previously built the Brucejack mine in British Columbia.

BMO Capital Markets

BMO Capital Markets is a Canadian investment bank whose analyst Andrew Mikitchook commented that the study further de-risks Richmond Hill.

The details

Richmond Hill is an open-pit, heap-leach operation about 320 km west of Pierre, South Dakota, on a 180-sq.-km land package near the historic Homestake mine, which produced about 40 million oz. of gold before ceasing operations in 2002. Reclassifying material previously considered suitable for heap leaching removed about 1 million oz. of gold from the plan, while larger crushers and the cost of a leach pad in a steep-sided valley drove much of the capital increase.

Timeline

  1. 2025: Previous assessment projected a 17-year mine life and $1.6 billion NPV.

  2. Nov. 23, 2026: Proven and probable reserves totaled 2.16 million oz. of gold.

  3. Nov. 24, 2026: Prefeasibility study released; shares fell the following day.

  4. Mid-2027: Feasibility study due.

  5. 2029: Targeted start of production.

Market Landscape

Richmond Hill is being developed on land near the Homestake mine, which produced about 40 million oz. of gold over more than 145 years before closing in 2002. The project revives gold mining in the region on a far smaller, heap-leach scale than that historic operation.

For South Dakota residents and investors, the project's 2029 start target and nine-year mine life define the timeline for any local jobs and tax revenue. Investors should note that the revised plan lowers recovery and output assumptions and depends on future permits and financing.

The takeaway

The revised study shows that a shorter, more capital-intensive mine can still improve projected value, but the economics are not yet confirmed until the mid-2027 feasibility study and permitting are complete.

What happens next

Dakota Gold plans a feasibility study in mid-2027 to confirm the economics, with production targeted for 2029 subject to permits and a construction decision.