Boeing Misses 787 Rate 10 Goal in Charleston
Boeing will not reach its target of 10 787 Dreamliners a month from North Charleston in 2026, with the higher rate now pushed to 2029.
Updated on Nov. 1, 2026 in Business

Boeing will not meet its goal of rolling out 10 787 Dreamliners a month from its North Charleston factory in 2026, and will not increase production to 12 planes a month until 2029. The factory is currently producing 8 aircraft per month, with jet engine shortages from GE Aerospace cited as the biggest impediment.
Why it matters
The delay affects Boeing's delivery schedule and cash flow for one of its key widebody programs, which is central to the company's financial recovery. For North Charleston, the slower ramp-up shapes the timing of the expanded production capacity and associated jobs.
Boeing delivered 62 787 Dreamliners through September 2026 and expects 90 to 100 deliveries this year, likely toward the lower end. The company estimates annual cash flow of $2 billion this year against a $10 billion target for 2029, and its 787 backlog is approaching 1,200 planes.
The players
Boeing
Boeing is the American aerospace manufacturer that builds the 787 Dreamliner and the 737 Max, and it is the company whose production targets are the subject of this report.
GE Aerospace
GE Aerospace is the American jet engine maker whose delayed engine deliveries are the main constraint on Boeing's 787 production rate.
The details
Boeing consolidated all 787 production at its North Charleston campus in 2021 and broke ground on a second 787 assembly plant about a year ago, a $1 billion investment that will add a third production line. The company says the rate step to 10 per month is expected to begin by December 31, but engine delivery delays from GE Aerospace continue to constrain output.
Timeline
2021: Boeing consolidates 787 production at its North Charleston campus.
2025: The 787 program recovers as customers resume ordering the aircraft.
About a year before publication: Boeing breaks ground on its second 787 assembly plant.
By December 31, 2026: Boeing targets the start of its transition to Rate 10.
2029: Boeing expects to raise the 787 production rate to 12 planes a month.
Market Landscape
Boeing consolidated all 787 production at North Charleston in 2021, and the current delay pushes its planned rate increases further out than originally planned. The slower ramp leaves the company's 787 backlog of roughly 1,200 planes to be worked through at a pace set by engine supply rather than demand, since customers resumed ordering the aircraft in 2025.
Buyers and airline customers waiting on 787 deliveries should expect the 2026 delivery count to land at the lower end of the 90 to 100 range. For the Charleston area, the second assembly plant and its planned jobs will arrive on a slower timeline than the original rate goal implied.
The takeaway
Production timelines for large aircraft depend as much on suppliers like GE Aerospace as on the assembly lines themselves, so engine delivery is the number to watch. Tracking that supply will show whether the 2029 rate target holds.
What happens next
Boeing expects the transition to Rate 10 to begin by December 31, 2026, and expects the majority of the expanded Charleston capability to come online late next year.
Further reading
For more on the industry behind this delay, see Manufacturing coverage of North Charleston.
Source note: This article includes information reported by Post and Courier.