Ashley River Crossing to Open in Summer 2027

The bike-pedestrian bridge linking West Ashley and downtown Charleston is under construction and on schedule and budget.

Updated on Nov. 13, 2026 in Construction

Wide view of a cable-stayed bridge with a tall white pylon and fanned steel cables spanning a tidal river, flanked by marsh grass and live oaks under a pale sky.
Construction continues on the Ashley River Crossing, a bike-pedestrian bridge linking West Ashley and downtown Charleston, which remains on schedule and budget for a summer 2027 opening. AI Illustration. Upload story photo >

Live Poll

Do you support spending public money on new bike and pedestrian bridges in your city?

Construction of the Ashley River Crossing, a bike-pedestrian bridge spanning the Ashley River between downtown Charleston's hospital district and West Ashley, began in January 2025. The project is on schedule and on budget for completion in summer 2027.

Why it matters

The bridge will directly connect the West Ashley Greenway, Maryville Bikeway and the downtown Medical District for cyclists and pedestrians. Mobility advocates and city leaders expect heavy use across the region once it opens.

The project carries an estimated total cost of $90 million, with construction beginning in January 2025 and completion targeted for summer 2027. The breakdown of funding shares among the federal government, city, county, state and Medical University of South Carolina has not been detailed.

The players

City of Charleston

The city of Charleston is the municipal government of the South Carolina port city and a contributor to the project's funding.

Medical University of South Carolina

The Medical University of South Carolina is a state-supported academic medical center in downtown Charleston and a funding contributor to the bridge.

The details

The bridge is relatively short and flat and has a cable-stayed, swing-span design, with an elevated landing pad, pedestrian roundabout, slip lane intersection on the downtown side, and an Ashley River viewing platform. Surrounding intersections are being upgraded to improve safety for bikers and pedestrians getting on and off the bridge, which connects to Brittlebank Park and Bee Street.

Timeline

  1. Years before January 2025: Project moved through several design phases and sat in development limbo.

  2. January 2025: Construction on the bridge began.

  3. Summer 2027: Scheduled completion of the bridge.

Construction Outlook

The Ashley River Crossing is largely federally funded, placing it among multimodal projects that rely on federal transportation money to move from planning into construction. Its progress after years of design revisions shows how such funding can revive projects stalled in development.

Cyclists and pedestrians will gain a direct connection between the West Ashley Greenway, Maryville Bikeway and the downtown Medical District once the bridge opens in summer 2027. Upgraded intersections at each end are intended to make getting on and off the bridge safer for those traveling by bike or on foot.

The takeaway

The bridge shows that a project delayed for years in planning can reach construction when funding aligns across federal, state and local partners. Residents planning to bike or walk between West Ashley and downtown Charleston can expect a new route when it opens in summer 2027.

Further reading

Explore more Charleston construction projects to see how major infrastructure is reshaping the city.

Source note: This article includes information reported by Charleston City Paper.