Coast Guard Completed Base Charleston Pier Project
The $132.5 million reconstruction of Pier November finished 60 days ahead of schedule in Charleston.
Updated on Oct. 9, 2026 in Construction

Live Poll
Do you support large federal infrastructure investments to upgrade aging military or public facilities?
The Coast Guard has finalized the $132.5 million reconstruction of Pier November at Base Charleston. The upgraded facility, which spans 1,190 feet in length, is now capable of accommodating up to five Coast Guard cutters.
Why it matters
This infrastructure upgrade provides essential support for Coast Guard cutters, crews, and regional operations. Base Charleston is positioned to serve as a hub for significant concentrations of Coast Guard personnel and assets.
The new structure measures 1,190 feet long by 80 feet wide and was completed 60 days ahead of the original construction schedule. The project was supported by the $25 billion One Big Beautiful Bill Act and Fiscal Year 2019 supplemental funding.
The players
Coast Guard
This federal military branch is responsible for maritime safety, security, and stewardship throughout the United States.
The details
Crews executed the project by demolishing the existing pier, repairing collapsed bulkheads, and performing dredging work. Workers also upgraded shoreside utilities and cleared away remnants of previous repairs discovered during the construction process.
Timeline
Fiscal Year 2019: The Hurricane Supplemental provided initial project funding.
Market Landscape
The project follows the investment priorities established by the One Big Beautiful Bill Act to modernize federal maritime infrastructure. This expansion strengthens the operational capacity of Base Charleston relative to other coastal facilities in the region.
The completion of the pier enhances the operational capabilities of the local base, potentially increasing activity and asset presence in the harbor. Local businesses and residents may see sustained construction activity as further engineering and medical facilities are planned for the site.
The takeaway
This successful early delivery demonstrates effective resource management in large-scale government infrastructure projects. The site will continue to evolve as the Coast Guard proceeds with planned facility upgrades.
Further reading
Find more details on regional infrastructure developments at Charleston Construction.