Penn State Approves Airport and Thompson Hall Upgrades
Trustees also approved the sale of the Penn State York campus to York College of Pennsylvania.
Updated on Nov. 20, 2026 in Education

Penn State trustees approved up to $12.2 million for runway lighting and navigational aid upgrades at State College Regional Airport. Trustees also approved up to $16.6 million to renovate Thompson Hall at University Park.
Why it matters
The airport project replaces aging electrical infrastructure with energy-efficient LED lighting and is largely funded by Federal Aviation Administration grants. The Thompson Hall renovation modernizes bathrooms and student amenities while adding 14 new beds for the State College community.
Penn State trustees approved up to $12.2 million for airport lighting upgrades and up to $16.6 million for the Thompson Hall renovation. Penn State research expenditures reached a record $1.48 billion, a 2% increase over the previous year.
The players
Penn State
The Pennsylvania State University is a public research university with campuses across the state, including University Park and the York campus.
York College of Pennsylvania
York College of Pennsylvania is a private college in York, Pennsylvania, that agreed to acquire the Penn State York campus.
The details
The airport project was approved by voice vote and will replace aging electrical infrastructure on runway 06/24. The Thompson Hall project, designed by Hoffman Leakey Architects of Bellefonte, follows an approach similar to Hamilton Hall and McKee Hall to create a more consistent experience across the West Residence Halls.
Timeline
November 13, 2025: Trustees approved the airport upgrades, Thompson Hall renovation and York campus sale.
May 2027: Airport runway construction is scheduled to begin, mostly at night to limit disruptions.
End of spring 2027 semester: The Penn State York campus will close.
November 2027: The airport runway project is scheduled for substantial completion.
May 6, 2027: Agricultural trustee delegate election and alumni trustee ballot counting.
Big Picture
Penn State's record $1.48 billion in research expenditures, up 2% from the prior year, marks continued growth in the university's sponsored research activity. The board's capital approvals for the airport and Thompson Hall sit alongside that research growth as part of its ongoing campus investment.
State College Regional Airport passengers may notice nighttime construction as runway lighting is replaced with energy-efficient LED systems. Students and staff at University Park will see improved bathrooms and amenities once the Thompson Hall renovation, which adds 14 new beds, is complete.
The takeaway
Capital decisions at Penn State are moving resources toward airport infrastructure, residence halls and research capacity while consolidating the York campus. Readers tracking the university's direction can watch the 2027 construction timelines and the York closure as indicators of how these commitments unfold.
What happens next
Airport runway construction is scheduled to begin in May 2027 and reach substantial completion in November 2027. The Penn State York campus will close at the end of the spring 2027 semester.