Water Service Halts on North Washington Avenue Monday
Pennsylvania American Water is installing a valve on the 100 block of North Washington Avenue ahead of a downtown main replacement.
Updated on Nov. 15, 2026 in Business

Live Poll
Do you think downtown road closures for infrastructure upgrades are worth the disruption?
Pennsylvania American Water will close the 100 block of North Washington Avenue in downtown Scranton on Monday, November 16, 2026, with water service shutting off around 8 p.m. Contractor R.L.E. Enterprises will install a valve as part of the utility's downtown work.
Why it matters
The valve is needed to connect to a new water main planned for next year, and the work follows two large water-main breaks in downtown Scranton this July that disrupted the area. The utility has accelerated a $5 million replacement project by one year in response.
The $5 million project replaces 1 mile of downtown mains, with the schedule moved up from 2028 to 2027 after the utility's accelerated timeline. Expected reopening is Tuesday, though the stub does not confirm the duration of any remaining phases.
The players
Pennsylvania American Water
A regulated water utility serving customers across Pennsylvania, responsible for the downtown Scranton main replacement and valve work.
R.L.E. Enterprises
The contractor performing the valve installation on North Washington Avenue for Pennsylvania American Water.
The details
Contractor R.L.E. Enterprises will stage equipment and begin excavation on the block, which is closed to traffic because there is not enough room to safely accommodate vehicles during construction. The 100 block, between Lackawanna Avenue and Biden Street, previously closed for utility work without significant issues.
Timeline
July 27, 2026: A 24-inch main dating to 1885 broke in front of the William J. Nealon Federal Building.
September 2026: Pennsylvania American Water announced it would accelerate the $5 million project by one year.
Monday, November 16, 2026: The block closes and water service shuts off around 8 p.m.
Tuesday, November 17, 2026: Water service is expected to be restored and the road reopened.
Spring 2027: Construction on the larger downtown main is expected to begin.
Market Landscape
The valve work follows two large water-main breaks in downtown Scranton in July, the first a 24-inch main from 1885 that broke about two weeks before a second break. Pennsylvania American Water's decision to accelerate its $5 million replacement by one year reflects the aging infrastructure revealed by those failures.
Drivers and businesses on the 100 block of North Washington Avenue should expect the road closed and water service off starting around 8 p.m. Monday, with restoration expected Tuesday. Residents should plan for disruption as downtown replacement work continues in phases.
The takeaway
Aging downtown infrastructure is driving accelerated repairs, and short-term closures like this one are the visible step toward the longer replacement schedule.
What happens next
Construction on the larger downtown water main is scheduled to begin in spring 2027, with replacement work to be completed in phases.
Further reading
Find more on Scranton utilities as the downtown water-main work moves forward.
Live Poll
Do you think downtown road closures for infrastructure upgrades are worth the disruption?






