Hawthorne Footbridge to Finish in 2030

Oregon Department of Transportation projects the $32 million Bend footbridge over U.S. Highway 97 will be completed in the first half of 2030.

Updated on Nov. 26, 2026 in Business

Hawthorne Footbridge to Finish in 2030

Live Poll

Do you trust Bend's local government to finish big projects on schedule?

The Oregon Department of Transportation projects construction of the Hawthorne Crossing footbridge over U.S. Highway 97 and Burlington Northern Santa Fe Railway tracks will finish in the first half of 2030. The timeline is about a year and a half later than the previous completion date, and the City of Bend's website has not yet been updated.

Why it matters

The delay is attributed to questions about the availability of steel needed to build the bridge, which is a key constraint on the project. The bridge is a central piece of Bend's Midtown Crossings effort to connect the Bend Central District.

The footbridge carries a $32 million price tag, the most expensive of Bend's Midtown Crossings projects, funded largely by federal, state and congressional sources. Final designs and construction bids remain pending, so the total cost and schedule could still change.

The players

Oregon Department of Transportation

The state agency responsible for Oregon's highways and bridges, overseeing the design and construction of the Hawthorne Crossing footbridge.

City of Bend

The municipal government of Bend, Oregon, which has funded portions of the bridge and manages the Midtown Crossings effort.

The details

The 18-foot-wide path will span U.S. Highway 97 and the railroad tracks, with steel trusses assembled on Hawthorne Avenue and lifted into place. The City Council selected a cable-supported design in 2024 before pivoting to a truss-style design nearly a year later due to unexpected costs, and ODOT published new design details online on November 20.

Timeline

  1. 2020: Voters approved a $1 million City transportation bond for the bridge.

  2. 2024: The Bend City Council chose a cable-supported bridge design.

  3. November 20, 2026: ODOT published new renderings and design details online.

  4. December 3, 2026: An in-person open house with the City is scheduled.

  5. Summer 2027: Final bridge designs are expected to be completed.

Market Landscape

The bridge's $20 million in funding comes from Biden-era federal infrastructure money, which has helped fund local transportation projects across Oregon. The delay tied to steel availability reflects the broader pressure that rising material costs are placing on public infrastructure schedules.

Drivers on U.S. Highway 97 should expect up to two full-weekend closures during construction. Pedestrians and cyclists will gain an 18-foot-wide path crossing the highway and railroad tracks once the bridge opens.

The takeaway

Project timelines for public infrastructure can shift when material markets tighten, so residents tracking Bend's Midtown Crossings should watch for the updated city schedule and the December 3 open house.

What happens next

Final bridge designs are expected in summer 2027, with construction bids going out in fall 2027. Up to two full-weekend closures of U.S. Highway 97 are expected during construction.

Further reading

Explore more Bend construction projects to see how the Midtown Crossings effort is taking shape.

Source note: This article includes information reported by The Source - Bend, Oregon.