Oregon Counties Approve Two Clean Energy Projects
Developers switched to county approval under House Bill 4031, bypassing a state siting process that averages 600 days.
Updated on Nov. 27, 2026 in Government

Live Poll
Should Oregon speed up approval of clean energy projects in your community?
Two clean energy developers switched from state to county jurisdiction under House Bill 4031, which Oregon lawmakers passed in February 2026. In September 2026, Morrow County approved a solar array and Gilliam County approved a 69-turbine wind farm.
Why it matters
Oregon projects take an average of 600 days to reach a state siting decision, and a Department of Energy Berkeley Lab report ranked the state last among states for wind and solar approval times. Lawmakers cited these delays as the main reason for passing the bill, and federal clean energy tax credits now have an expiration date.
The Oregon Department of Energy identified seven renewable projects eligible to switch to county jurisdiction, and two have done so. Thirteen other clean energy projects did not qualify and remain in the state process, and it is not yet clear whether the two county-approved projects will capture the federal tax credits.
The players
Oregon Energy Facility Siting Council
The state body that has historically reviewed large energy facility applications in Oregon, and which projects under House Bill 4031 can now bypass in favor of county review.
Rep. Mark Gamba
An Oregon state representative from Milwaukie who has said he plans to tighten the state's siting process in the 2027 legislative session.
Rep. John Lively
An Oregon state representative from Springfield whose home district is connected to the clean energy siting debate.
The details
Under House Bill 4031, developers of certain clean energy projects apply directly to county governments instead of the Energy Facility Siting Council. The State Energy Facility Siting Council approved the Yellow Rosebush Energy Center solar farm in Wasco County on September 18, 2026, and county approval for the two switched projects took months rather than years.
Timeline
February 2026: Oregon Legislature passed House Bill 4031.
September 2026: Morrow and Gilliam counties approved the two projects.
September 18, 2026: The state council approved the Yellow Rosebush Energy Center.
2027 legislative session: Rep. Mark Gamba plans to tighten the state siting process.
Political Context
The approval shift comes as the One Big Beautiful Bill Act set an expiration date on federal clean energy tax credits, raising the financial stakes of slow state reviews. Critics of the state process argue that Oregon's 47th national ranking for new clean energy production reflects approval delays rather than a lack of projects.
For residents near proposed solar and wind sites, the switch to county review changes where public hearings and land-use decisions take place. Projects that stay in the state process will continue to face the long approval timeline that lawmakers said prompted the bill.
The takeaway
Faster county review may help some clean energy projects meet federal tax deadlines, but the bill only reaches a limited set of developers. Whether it changes Oregon's standing depends on how many of the remaining 13 projects can follow.
What happens next
Rep. Mark Gamba plans to tighten the state's siting process in the 2027 legislative session.
Further reading
For more on how state agencies handle these decisions, see Government coverage of Oregon's policy debates.
Source note: This article includes information reported by Lookout Eugene-Springfield.