Oregon Rail Projects Have Faced Costly Delays
Two state-funded rail centers have struggled to reach full operation despite millions in public investment.
Updated on Oct. 9, 2026 in Transportation

Live Poll
Do you trust your local government to effectively manage large-scale public infrastructure projects?
Oregon rail infrastructure projects have remained largely idle after suffering significant budget overages and operational delays. More than $70 million in public funds has been committed to the centers, which were initially designed to increase export efficiency.
Why it matters
The initiatives were intended to reduce truck emissions and lower shipping costs for local farmers, but a lack of rail company collaboration has stalled progress. These delays have left major state-funded facilities underutilized since their construction.
The Treasure Valley Reload Center finished $18 million over budget by 2024, while the Mid-Willamette Valley Intermodal Center ran $10 million over its budget. These projects were part of a $50 million grant allocation from a larger $5.3 billion legislative package.
The players
Wyoming Colorado Railroad
This company is negotiating a potential purchase and lease agreement for the unfinished Treasure Valley Reload Center.
Orion
This organization is currently in negotiations with Linn County to utilize the intermodal facility for the transport of biodiesel.
Oregon Department of Transportation
This state agency oversees the planning and funding of major transportation infrastructure projects across the region.
Malheur County
This local government body is the primary authority overseeing the development and management of the Treasure Valley project.
Linn County
This county government manages the Mid-Willamette Valley Intermodal Center and facilitates its ongoing negotiations with private partners.
The details
The Mid-Willamette Valley Intermodal Center in Millersburg currently hosts only occasional material movement by a local roofing company. Meanwhile, Malheur County is negotiating an agreement with the Wyoming Colorado Railroad to finish construction at the Treasure Valley Reload Center in Nyssa.
Timeline
2017: The Oregon Legislature approved a $5.3 billion transportation funding package.
November 2022: Construction concluded at the Mid-Willamette Valley Intermodal Center.
2024: The Treasure Valley Reload Center project was reported at $18 million over budget.
October 8, 2026: The Oregon Department of Transportation presented an update on the project status.
Late 2026 or early 2027: Potential operations for biodiesel transport could begin at the Mid-Willamette facility.
Market Landscape
These projects represent a recurring challenge in public infrastructure, where initial legislative funding often fails to account for the complexities of private rail partnerships. The idle facilities highlight the difficulty of aligning public export goals with the operational needs of major rail carriers.
Taxpayers continue to foot the bill for facilities that currently provide limited public utility or economic return. While officials hope for operations to begin soon, the lack of consistent rail service remains a barrier to projected savings for local growers.
The takeaway
Large-scale public infrastructure projects frequently face long timelines due to the need for alignment with private sector logistics. Success often depends on securing firm partnerships with rail companies long before construction is finalized.
Further reading
For more information on state infrastructure updates, visit the Transportation section.