Council Approves $315,000 Main Street Roundabout Rebuild

Stillwater's City Council voted 5-0 to rebuild the roundabout at Main Street and 10th Avenue after bids came in above estimates.

Updated on Nov. 19, 2026 in City Hall

Wide view of a suburban roundabout with a stone-walled central island, fresh asphalt, young trees, and a parked excavator on the west lane under morning light.
Stillwater's City Council voted 5-0 on Monday to rebuild the Main Street and 10th Avenue roundabout for $315,000 after bids came in well above estimates. AI Illustration. Upload story photo >

Live Poll

Do you trust your local government to manage public project spending well?

The Stillwater City Council voted 5-0 on Monday to proceed with rebuilding the roundabout at Main Street and 10th Avenue. The project now carries a $315,000 price tag, including contingencies, after the city selected a $260,723 bid from MK Excavation, LLC.

Why it matters

The rebuild cost rose well above the city's earlier estimates, with the winning bid about 50% higher than originally projected. The council's choice to keep the roundabout rather than convert the intersection to a four-way stop, which would cost about $425,000, shapes how Stillwater manages its traffic and transportation spending.

The council's 5-0 vote set the rebuild at $315,000, paid from the Transportation Sales Tax Fund, with $165,000 authorized for engineering design earlier in the process. The four-way stop alternative was estimated at about $425,000, or 30% more than May figures, and the council has not addressed how any further cost overruns would be covered.

The players

Stillwater City Council

The elected legislative body of the city of Stillwater, responsible for approving municipal spending and infrastructure projects such as the Main Street roundabout.

MK Excavation, LLC

The contractor whose $260,723 bid was selected by the city to carry out the roundabout rebuild.

The details

The rebuild includes full reconstruction of the west lane, new striping and signage, updated landscaping, a hatchet stone wall around the statue, and solar lighting. Officials attributed the cost increases to disrupted unit prices, specialty stone and decorative lighting work, and complicated traffic and pedestrian conditions at a busy intersection.

Timeline

  1. May: City Council approved the roundabout rebuild and engineering design funding.

  2. Monday: Council voted 5-0 to proceed with the rebuild at a regular meeting.

  3. January: Planned start of rebuild construction.

  4. March: Target completion before The Mid-South bike race.

Legislative Context

The project's cost path departs from the May approval, when the conceptual design was estimated at $145,000, and has since climbed to $162,000 in revised design figures and $315,000 in total rebuild cost. The council's decision to keep the roundabout instead of switching to a four-way stop reflects the trade-off it weighed against the May alternatives.

Drivers passing through the Main Street and 10th Avenue intersection should expect construction beginning in January, with the work targeted for completion before March. The rebuild is funded from the city's Transportation Sales Tax Fund rather than a new tax, so the immediate effect on household costs is limited to the project's use of existing transportation dollars.

The takeaway

Large municipal projects can grow well beyond early estimates once bids arrive, so residents watching local infrastructure spending should track contract figures as well as initial approvals. The Stillwater roundabout case shows how a single intersection decision can carry costs that rival the alternatives it was meant to beat.

What happens next

Rebuild construction is planned to begin in January and finish before The Mid-South bike race in March.

Further reading

For more on how local government decisions like this one are made, browse City Hall coverage across Stillwater.

Source note: This article includes information reported by Stillwater News Press.