Crews Begin Pouring Elevated Decks at Continental Coliseum
The $990 million downtown Oklahoma City arena has moved into elevated concrete work on its southeastern side.
Updated on Nov. 16, 2026 in Construction

Live Poll
Do you support using city sales taxes to fund new sports arenas?
Crews have begun pouring elevated concrete decks for the $990 million Continental Coliseum in downtown Oklahoma City, starting on the building's southeastern side. More than 18 decks are being installed as construction advances on the 750,000-square-foot arena.
Why it matters
The elevated decks establish the arena's mezzanine and concourse levels, marking a visible stage of construction for Oklahoma City residents watching the downtown project take shape. The work keeps the arena on track for completion in late summer 2028, ahead of the 2028-29 NBA season.
The $990 million arena is funded in part by a one-cent sales tax on retail purchases in Oklahoma City and a $50 million contribution from the Oklahoma City Thunder ownership group. Nearly 175 workers are currently constructing the loading dock walls along the eastern side.
The players
Oklahoma City Thunder
The Oklahoma City Thunder is the NBA franchise whose ownership group is contributing $50 million toward the arena's funding.
The details
Crews began pouring concrete for the building's substructure in July 2026, including pier caps and two large mat foundations. The arena occupies the block bounded by Reno Avenue, Ron Norick Boulevard, Sheridan Avenue and E.K. Gaylord Boulevard and will feature a 360-degree glass curtain wall.
Timeline
December 2023: Voters approved the arena funding plan with 71% support.
March 2026: Arena construction commenced.
July 2026: Crews began pouring substructure concrete, pier caps and mats.
November 16, 2026: Elevated concrete deck installation began.
Late summer 2028: Arena completion expected ahead of the 2028-29 NBA season.
Roadmap
Voters approved the arena's funding plan with 71% support in December 2023, combining a one-cent retail sales tax with a $50 million Thunder ownership contribution. The current elevated-deck work is the construction phase that follows that approval, moving the project toward its late-summer 2028 completion.
Residents and visitors in downtown Oklahoma City will see ongoing construction activity around the block bounded by Reno Avenue, Ron Norick Boulevard, Sheridan Avenue and E.K. Gaylord Boulevard. The arena's eventual 17,200-seat capacity will shape event traffic and downtown activity once it opens.
The takeaway
The arena's elevated decks signal that the $990 million project has moved from foundations into the structure that defines its interior levels. Readers tracking Oklahoma City's downtown development can expect the next visible milestones through 2027 and 2028.
What happens next
Crews are expected to continue installing the remaining elevated concrete decks, with the arena targeted for completion in late summer 2028.