SPP Board Withdraws Mathewson-Redbud Transmission Line

The Southwest Power Pool's board voted to pull a roughly 40-mile high-voltage line planned between Piedmont and Luther in Oklahoma.

Updated on Nov. 18, 2026 in Utilities

SPP Board Withdraws Mathewson-Redbud Transmission Line

Live Poll

Should your community be willing to host new high-voltage power lines?

The Southwest Power Pool's board of directors voted on a Tuesday to withdraw the Mathewson-Redbud transmission project, following a recommendation from SPP staff. The roughly 40-mile high-voltage line would have connected a Piedmont substation to a Luther power plant, both owned by Oklahoma Gas & Electric.

Why it matters

The project was intended to ease congestion as electricity demand grows across the region, and its withdrawal changes the grid plan for central Oklahoma. SPP's CEO stated that not proceeding with the project provides greater benefits at lower cost.

The withdrawn Mathewson-Redbud line was planned at about 40 miles with a latest expected development cost of $89.52 million, up from a headline figure of $72 million. The extraction does not explain the difference between these two cost figures or what replacement measures SPP will adopt.

The players

Southwest Power Pool

A regional transmission organization that coordinates the high-voltage electric grid across parts of the central United States.

Transource

A transmission development company formed as a partnership between a parent of Public Service Company of Oklahoma and Evergy, which was developing the line.

The details

Transource, a partnership between the parent of Public Service Company of Oklahoma and Evergy, was developing the line, which was expected to enter service in 2027 according to its website. Residents along the proposed path raised concerns about potential environmental impacts before the board acted.

Timeline

  1. June: An Oklahoma Watch investigation reported that companies seeking to build data centers were attracted to power infrastructure in Piedmont and the corridor.

  2. Tuesday, November 2026: The SPP board of directors voted to withdraw the project.

  3. 2027: The line's original expected in-service date.

Roadmap

The withdrawal follows a June Oklahoma Watch investigation finding that companies seeking to build data centers were drawn to power infrastructure in Piedmont and along the line's corridor. It marks a shift in how the Southwest Power Pool plans to meet electricity demand growth across the state.

Oklahoma electricity customers will not see the transmission line built as originally planned, so the congestion relief it was meant to provide will come from a different plan. Residents near the former route no longer face the proposed construction along that corridor.

The takeaway

Grid projects can be reconsidered before construction when staff review shows lower-cost alternatives, so readers following Oklahoma power planning should track SPP board decisions for the replacement strategy.

Further reading

For more on how grid planning is shifting, see Utilities coverage across the state.