Dayton Declares Emergency for Vacant 27-Story Tower

The city is stabilizing the empty downtown office building after a potential buyer backed out of a purchase deal.

Updated on Nov. 24, 2026 in City Hall

Isometric editorial illustration of a single tall, plain vacant office tower with uniform dark windows rising from a quiet street edge, with a thin perimeter line on the sidewalk.
Dayton City Manager Shelley Dickstein declared an emergency in mid-September to speed stabilization of the vacant 27-story tower at 10 W. Second St. after a buyer backed out. AI Illustration. Upload story photo >

Live Poll

Do you trust Dayton's city government to manage downtown buildings well?

Dayton City Manager Shelley Dickstein declared an emergency in mid-September to speed up hiring a contractor for stabilization, management and preservation of the vacant 27-story office tower at 10 W. Second St. The move follows a potential buyer's withdrawal from a purchase deal, leaving the city responsible for the building.

Why it matters

The emergency declaration shortens the timeline for stabilizing a large empty structure in Dayton's downtown, where the city must keep utilities and some elevators running. Projected holding costs mean the city will carry expenses for the property while it evaluates future development options.

The Dayton City Commission approved spending $83,000 to drain the building's systems, and the city projects about $400,000 in utility and stabilization costs through year-end. The city has not said which buyer or development plan will follow, and an evaluation of future options is still underway.

The players

Shelley Dickstein

Dayton City Manager who declared the emergency to accelerate stabilization and management work on the vacant tower.

City of Dayton

The municipal government that now holds management responsibility for the vacant 27-story office building and its ongoing holding costs.

The details

The city regained management of the 27-story building, formerly known as the KeyBank Tower and earlier as the Mead Tower, in April. A downtown property owner had held a purchase option on the tower and did not follow through, and the city has agreed not to pursue more than $600,000 in unpaid rent and tax obligations tied to the property. Officials say the city must keep utilities and some elevators in service while stabilization work proceeds.

Timeline

  1. Three years ago: A downtown property company signed a ground lease with a purchase option for the tower.

  2. Last year: The city spent at least $3.5 million stabilizing the empty building at 34 N. Main St.

  3. April: The city regained management responsibility of the 10 W. Second St. property.

  4. Mid-September: The city manager declared the emergency to speed up contractor hiring.

  5. End of the year: Projected utility and stabilization cost window ends.

Political Context

The city's emergency declaration for the 10 W. Second St. tower follows its earlier $3.5 million stabilization of the empty building at 34 N. Main St. last year. Taken together, the two efforts show Dayton carrying repair and holding costs for large vacant downtown properties it has taken on.

Dayton taxpayers will fund the utility and stabilization costs for the vacant tower while the city weighs future development options. The emergency declaration means the city can hire contractors on a faster timeline, which could affect how quickly the building is stabilized and what it costs over the coming months.

The takeaway

Vacant downtown buildings can carry substantial ongoing costs even after a buyer falls through, and Dayton's recent spending shows how those costs accumulate for the city.

Further reading

For more on how city officials are handling Dayton's vacant downtown buildings, see City Hall.

Source note: This article includes information reported by Dayton Daily News.