NYC Launches $108.7M Broadway Bridge Rehabilitation
The New York City Department of Transportation is repairing the Harlem River crossing linking Manhattan, Marble Hill and Inwood, with work expected to finish in early 2028.
Updated on Nov. 26, 2026 in Construction

Live Poll
Do you think the city's major infrastructure projects are worth the commuting disruption?
The New York City Department of Transportation has begun a $108.7 million rehabilitation of the Broadway Bridge, which connects Marble Hill to Inwood over the Harlem River. Traffic lanes have been closed for construction work on the 1962 structure.
Why it matters
The project is intended to update aging infrastructure and improve the crossing for pedestrians and cyclists. The bridge carries the No. 1 subway line and several bus routes, so the work affects daily commuters in Upper Manhattan and the Bronx.
The $108.7 million rehabilitation budget covers structural repairs, electrical upgrades, a new bicycle lane and sidewalk work on a bridge built in 1962. Lane closures run on set schedules, with the Bronx-bound right lane shut from 7 a.m. to 3 p.m. through Dec. 11, while the full scope of remaining repairs is not yet detailed.
The players
New York City Department of Transportation
The city agency responsible for maintaining and rehabilitating the city's bridges, tunnels and roadways, including the Broadway Bridge over the Harlem River.
Metro-North Railroad
A commuter rail line operated by the Metropolitan Transportation Authority, whose tracks run beneath the Broadway Bridge and are being protected during the strengthening work.
The details
Crews have removed sections of sidewalk, pedestrian fencing and roadway grating, and installed electrical conduits and fiberglass-reinforced panels for the new bicycle lane. Workers are also repairing concrete supports, replacing wiring and strengthening sections above the Metro-North Railroad tracks.
Timeline
1962: The Broadway Bridge was built and opened.
Dec. 11: The Bronx-bound right lane closure is scheduled to end.
Early 2028: The rehabilitation is expected to be completed.
Infrastructure Context
The Broadway Bridge project continues the New York City Department of Transportation's program of rehabilitating aging Harlem River crossings built in the mid-twentieth century. Its inclusion of a new bicycle lane places it within the city's broader effort to add cycling routes to older structures that were not designed for them.
Drivers and bus riders crossing between Manhattan and the Bronx should expect lane closures and possible delays until the Dec. 11 closure ends. Pedestrians and cyclists will gain a new bicycle lane and improved sidewalks once the project is finished.
The takeaway
Commuters who use the Broadway Bridge should plan for lane closures through the end of 2025 and check timing updates as construction phases change. The completed project should give pedestrians and cyclists a safer crossing over the Harlem River.
What happens next
The Bronx-bound right lane closure is scheduled to end on Dec. 11, and the full rehabilitation is expected to be completed in early 2028.
Further reading
Track more projects like this one in the Construction section for New York City.
Source note: This article includes information reported by The Riverdale Press.