MTA Flags Bushwick Subway Bottlenecks Without Funding

The agency has identified two bottlenecks affecting Bushwick and Ridgewood but has not allocated capital funds to fix either one.

Updated on Nov. 22, 2026 in Transportation

Isometric editorial illustration of two steel rail switches diverging from one trunk line in a dim tiled tunnel, beside an unlabeled signal housing.
The MTA has flagged two Bushwick and Ridgewood subway bottlenecks, including the Myrtle Avenue-Broadway junction used by the J, M and Z lines, but its capital plan includes no funding to fix either. AI Illustration. Upload story photo >

Live Poll

Do you think subway service in your neighborhood is getting worse?

The Metropolitan Transportation Authority has identified two major subway bottlenecks affecting Bushwick and Ridgewood, yet its current capital plan includes no funding to address either. A July 2026 report lists the Myrtle Avenue junction among 25 locations requiring further study.

Why it matters

Delays at the Myrtle Avenue-Broadway junction ripple across the J, M and Z lines that serve New York City neighborhoods on a daily basis. Without dedicated capital funding, the timeline for relief at these bottlenecks remains uncertain.

Between 11 and 20 of the roughly 560 J, M and Z trains scheduled on an average weekday lose more than three minutes at the Myrtle Avenue-Broadway junction, and the MTA has allocated $82.6 million for elevator installations at that station. The MTA has not said how much it would cost to fix the track and signal constraints behind the delays.

The players

Metropolitan Transportation Authority

The MTA is the public agency that operates New York City's subway and bus system and oversees its multiyear capital program.

The details

The MTA attributes delays at the Myrtle Avenue-Broadway junction, where J, M and Z trains merge, to slow track switches, aging signals and limited capacity. The July 2026 report rates the potential benefit of junction improvements as high and the estimated capital cost as medium.

Timeline

  1. January to October 2026: Approximately one in five M and J/Z trips ran more than five minutes late.

  2. July 2026: An MTA report listed the Myrtle Avenue junction among 25 locations needing further study.

  3. October 2028: Scheduled completion of the $82.6 million elevator installations at Myrtle Avenue-Broadway.

Market Landscape

The bottleneck findings sit inside the MTA's capital planning cycle, where studies identify problem locations before projects receive funding. Funding decisions for these two Bushwick and Ridgewood locations will determine whether they move from study to construction.

Riders on the J, M and Z lines who pass through the Myrtle Avenue-Broadway junction face recurring delays of several minutes on many weekdays. Commuters should expect continued schedule unreliability until funded repairs are scheduled.

The takeaway

Commuters who rely on the J, M and Z lines should build extra time into their trips, since the bottleneck fixes are not yet funded. Tracking the outcome of the planned study will show when relief may arrive.

What happens next

The MTA plans to study potential improvements at both identified Bushwick and Ridgewood bottleneck locations, with the Myrtle Avenue junction among the 25 sites in the July 2026 report.

Further reading

For broader context on how the system is tracking, see the Transportation coverage on New York City transit.

Source note: This article includes information reported by BKReader.