Buffalo Weighs Three Plans for Jefferson Avenue
The city's public works department held an open forum on phase two of the Jefferson Avenue Streetscape Project.
Updated on Nov. 19, 2026 in Politics

Live Poll
Would you support the Jefferson Avenue street improvements in your area?
The City of Buffalo Department of Public Works hosted an open forum Wednesday night on the second phase of the Jefferson Avenue Streetscape Project, covering the stretch from Best Street to Swan Street. Residents were presented with three alternative plans and could fine-tune the work to fit the community.
Why it matters
The second phase completes recent improvements to Jefferson Avenue and brings traffic signal, pavement and sidewalk upgrades to Buffalo residents who use the corridor. Public input at this preliminary design stage will shape which option moves forward.
The city presented three alternative plans for the Best Street to Swan Street segment at a public forum Wednesday night. The source does not state which alternative is preferred or when a final choice will be made.
The players
City of Buffalo Department of Public Works
The municipal department responsible for designing and maintaining city streets, sidewalks and infrastructure in Buffalo, New York.
The details
Residents attended the forum, chose among the alternative plans and could fine-tune the work to fit their community. The project includes improvements to traffic signals, pavement conditions and sidewalks along Jefferson Avenue.
Timeline
Wednesday, Nov. 18, 2026: Open forum on phase two of the Jefferson Avenue Streetscape Project held.
2027: Detailed design expected to be completed.
2028: Construction expected to begin.
2029: Construction expected to continue.
Political Context
The second phase extends the Jefferson Avenue Streetscape Project, which has already completed recent improvements to the corridor. The source does not report any formal opposition or dissenting views raised at the forum.
Drivers and pedestrians on Jefferson Avenue between Best Street and Swan Street can expect upgraded traffic signals, pavement and sidewalks once construction begins. Construction is not expected until 2028, so current travel on the corridor is not affected by this forum.
The takeaway
Residents who want a say in the final design of Jefferson Avenue should watch for further public forums as the detailed design is developed through 2027.
What happens next
The detailed design is expected to be completed in 2027, with construction planned to start in 2028 and continue into 2029.
Further reading
For more on how local officials make decisions like this, browse the City Hall coverage for Buffalo.
Source note: This article includes information reported by Wivb4.