Demolition Started at Albany Central Warehouse
Contractors have begun dismantling the rail bridge at the site of the historic 1927 Albany structure.
Updated on Sept. 21, 2026 in Commercial

Live Poll
Should your local government prioritize the demolition of abandoned buildings to help revitalize your community?
Crews have initiated major structural work at the Central Warehouse in Albany, beginning with the demolition of a rail bridge. The project marks a key step toward the complete removal of the 400,000-square-foot building by 2027.
Why it matters
Removing the rail bridge is a necessary hurdle for demolition due to the proximity of active Amtrak passenger rail lines. The site is being cleared after the Advance Albany County Alliance purchased the property for $50,000.
The project covers a 1.1-acre site containing the 400,000-square-foot, 11-story warehouse. Workers have already cleared 4,500 tons of asbestos from the structure.
The players
Advance Albany County Alliance
This organization is a local development entity that purchased the Central Warehouse property for future site redevelopment.
Jackson Demolition Services
This is a demolition contractor that previously sought a legal injunction to halt the destruction of the warehouse site.
The details
Contractors are utilizing cranes to dismantle the bridge during 12-hour overnight shifts over the coming week. The work proceeds following an appellate court decision in September 2025 that rejected a formal injunction sought by Jackson Demolition Services.
Timeline
The 11-story warehouse was originally erected in 1927.
Demolition for the site was first announced in August 2025.
An appellate court rejected a demolition injunction in September 2025.
Major structural work began on Monday, September 21, 2026.
Demolition of the building is scheduled to be complete in 2027.
Culture Shift
The demolition of the Central Warehouse reflects a broader trend of clearing decaying industrial infrastructure to make way for modern urban land use. This follows the pattern set by the September 2025 appellate court ruling that cleared the path for the project.
Residents should expect overnight noise and activity near the site as crews work 12-hour shifts to dismantle the bridge. The project progress will ultimately change the skyline of the neighborhood as the 11-story structure is leveled over the next year.
The takeaway
The removal of the rail bridge serves as the primary gateway for full-scale demolition of the massive warehouse structure. Local stakeholders should monitor official city updates for traffic or rail service adjustments during the overnight work periods.