Propel NY Energy Picks Contractors for $3.26B Project
New York Transco and the New York Power Authority selected contractors and suppliers as state regulators approved initial construction plans for the 90-mile transmission project.
Updated on Nov. 25, 2026 in Utilities

Live Poll
Do you trust large utility projects in your area to deliver promised benefits?
New York Transco and the New York Power Authority selected contractors and equipment suppliers for initial phases of Propel NY Energy, a $3.26 billion underground and submarine electric transmission project. The New York State Public Service Commission approved Phase 1 and Phase 2 Environmental Management and Construction Plans on Nov. 19.
Why it matters
The project is intended to increase energy capacity and improve resiliency for the electric system during high demand and severe weather incidents. Its routing through Long Island, Queens, the Bronx and Westchester County places the work directly in some of the state's most densely populated areas.
The $3.26 billion project spans 90 miles and includes three new Long Island substations, with construction phases still being sequenced by segment. Projected economic activity of $2.4 billion over the four-year build has not yet been independently verified against final contracts.
The players
New York Power Authority
The state-run public power utility that co-leads the Propel NY Energy transmission project and supplies electricity to public customers across New York.
New York Transco
The transmission company co-leading the Propel NY Energy project, responsible for building and operating the high-voltage electric infrastructure.
New York State Public Service Commission
The state regulatory body that oversees utilities and approved the project's Phase 1 and Phase 2 environmental and construction plans.
The details
Burns & McDonnell was selected as prime contractor for the three new Long Island substations, with Haugland Group and Hitachi Energy named as key subcontractors. The Crossing Group will perform trenchless drilling for the submarine cable crossing between New Rochelle and Glen Head, while LS Cable & System and Taihan will supply the underground transmission cables. Phase 1 focuses on vegetation management at the substations, and Phase 2 involves horizontal directional drilling at two landfall locations.
Timeline
Sept. 17: Project received major state siting approval.
June 22: Phase 1 vegetation management plan was initially filed.
Oct. 9: Phase 1 plan was updated after agency and public comments.
Nov. 19: Public Service Commission approved Phase 1 and Phase 2 construction plans.
Dec. 15, 6 p.m.: Quarterly public webinar on project updates.
Market Landscape
Propel NY Energy is part of New York's broader effort under the Climate Leadership and Community Protection Act to expand transmission capacity as the grid moves toward cleaner generation. The project's cost and contractor lineup reflect how large state-backed transmission builds are now typically assembled from multiple specialized firms.
Residents along the Long Island, Queens, Bronx and Westchester routes may see localized construction activity as crews work in segments across multiple sites. The project's economic activity is projected to support jobs and local spending during the four-year build, though its effect on household energy bills is not addressed in the source material.
The takeaway
Large transmission projects like Propel NY Energy are built in staged segments, so the timing of disruption and benefit will vary by location and phase. Readers along the route can track quarterly public updates to follow which work is scheduled next in their area.
What happens next
A quarterly public webinar on project updates is scheduled for Dec. 15 at 6 p.m., and more extensive construction is anticipated to begin in mid-2027.
Further reading
Explore more in Utilities coverage of New York's grid infrastructure and energy projects.
Source note: This article includes information reported by LI Press.