New York Legislators Seek Data Center Subsidy Answers
Lawmakers are calling for transparency regarding discounted electricity rates granted to data centers across the state.
Updated on Oct. 16, 2026 in Data Centers

Live Poll
Should data centers receive lower electricity rates through state-sponsored energy programs?
Assembly members Andrew Molitor and Ed Ra have signed a letter demanding transparency for electricity subsidies provided by the New York Power Authority. The push comes amid concerns over the cost-effectiveness of public economic development benefits for data centers.
Why it matters
Lawmakers are concerned that these massive power subsidies place an undue burden on infrastructure and electrical grid reliability. The requested financial data aims to determine if the public benefit justifies the scale of these energy discounts.
Residential customers pay $244 per megawatt-hour, while NYPA preferred power customers pay only $12.88. Since 2013, five Rockland County data centers have received $321 million in combined sales tax exemptions and power subsidies.
The players
Andrew Molitor
He is a New York State Assemblyman who has spearheaded the push for increased transparency regarding public utility subsidies.
Ed Ra
He is a New York State Assemblyman who has sought financial disclosures from the New York Power Authority regarding corporate energy discounts.
New York Power Authority
This is the state-owned utility responsible for managing power allocations and the ReCharge NY economic development program.
Scott Gray
He is a New York State Assemblyman who authored legislation requiring stricter oversight of electric service agreements for high-demand customers.
The details
Legislators have introduced bills, including A.10852/S.9182 and A.11419, to restrict ReCharge NY allocations and mandate Public Service Commission approval for electric service agreements. These measures seek to transition these high-demand energy negotiations to a more rigorous, case-by-case review process.
Timeline
Since 2013, data centers in Rockland County have received subsidies.
Legislation A.10852/S.9182 was introduced in April 2026.
Assemblyman Ed Ra appeared at a ribbon-cutting event in Summer 2026.
Assembly members signed the transparency letter in October 2026.
The Tech Race
This legislative push reflects a broader shift in how states handle the rapid expansion of digital infrastructure and its demand on local electrical grids. It signals a move away from legacy incentive programs toward more regulated, utility-approved energy agreements.
Residents may see changes in how the state balances industrial energy usage against residential rate stability if these transparency measures lead to policy reform. The outcome could dictate future electricity cost burdens for New York utility ratepayers.
The takeaway
The move by state lawmakers highlights a growing tension between incentivizing high-tech business growth and protecting local electrical grid reliability. Transparency in these agreements is seen as a necessary step for residents to understand the true cost of attracting major data centers.
Further reading
For more information on the industry's footprint, see Data Centers.