Bally's Commits to A's Stadium Infrastructure by 2028

Bally's told Nevada regulators that parking, utilities and connecting infrastructure for the Athletics' Las Vegas Strip stadium will be ready before the 2028 season.

Updated on Nov. 20, 2026 in Construction

Isometric editorial illustration of a bare concrete parking-structure frame beside an open utility trench on flat desert ground under a pale sky.
Bally's told Nevada regulators it will have parking, utilities and connecting infrastructure for the Athletics' $2.1 billion Las Vegas Strip stadium ready before the 2028 season. AI Illustration. Upload story photo >

Live Poll

Do you trust big companies to finish public projects they have promised?

Bally's told the Nevada Gaming Control Board that parking, utilities and connecting infrastructure for the A's stadium will be ready before the 2028 season. Gaming and Leisure Properties separately told the Las Vegas Stadium Authority it would increase its investment from $125 million to ensure essential infrastructure is completed on time.

Why it matters

The $2.1 billion stadium project on the Las Vegas Strip depends on infrastructure that a three-party agreement assigns to Bally's, the Athletics and Gaming and Leisure Properties. Bally's controlling shareholder's managing partner, Soo Kim, told regulators the company would develop and pay for the stadium entryway.

Gaming and Leisure Properties has raised its stadium commitment from $125 million, measured against a total $2.1 billion project. Unresolved are the cost split for Bally's portions of parking and utilities and whether the 2028 completion target holds.

The players

Bally's

Bally's is a casino-resort operator that is building multibillion-dollar resorts in Chicago and New York and is the controlling force behind the Strip stadium infrastructure obligations.

Soo Kim

Soo Kim is managing partner of Standard General, the controlling shareholder of Bally's, and testified before Nevada regulators on the company's stadium commitments.

Mike Dreitzer

Mike Dreitzer chairs the Nevada Gaming Control Board, which held the hearing at which Bally's made its stadium infrastructure commitments.

Standard General

Standard General is an investment firm that is the controlling shareholder of Bally's.

Gaming and Leisure Properties

Gaming and Leisure Properties is a real estate investment trust that owns the land under the stadium project and is raising its investment to $125 million or more.

The details

Soo Kim, managing partner of Standard General, Bally's controlling shareholder, told the Control Board in a 10-minute hearing chaired by Mike Dreitzer that Bally's would develop and pay for the stadium entryway. Bally's obligations include parking, utility connections and a connection between the Strip corners and the ballpark entrance, with the podium and shared accessway to follow once parking and utilities are complete.

Timeline

  1. November 19, 2026: Bally's special meeting before the Nevada Gaming Control Board on stadium concerns.

  2. Early 2027: Bally's expected to appear before the Control Board at least once, probably twice.

  3. April 2028: Deadline for parking, utilities and connecting infrastructure completion.

  4. 2031: Earliest expected completion of Bally's commercial area around the stadium.

Construction Context

Nevada's Gaming Control Board, which licenses casino operators under state gaming law, is now overseeing infrastructure commitments tied to the Athletics' stadium. The arrangement places a gaming licensee's construction obligations inside a sports-venue project rather than a resort build.

Bally's infrastructure timeline affects how soon the stadium's parking, utilities and Strip connections are usable for fans attending A's games. Delays could shift when the surrounding commercial area opens, which is not expected until 2031 at the earliest.

The takeaway

Commitments made to regulators can shape when a large project's supporting infrastructure is ready, so tracking Control Board filings offers a clear view of progress. Check the stadium's 2028 infrastructure target against future hearings to see whether it holds.

What happens next

Bally's is expected to appear before the Nevada Gaming Control Board at least once, and probably twice, in early 2027, when the company's stadium infrastructure commitments may be reviewed again.

Further reading

For more on large building projects shaping the valley, see Construction coverage across Las Vegas.

Source note: This article includes information reported by Las Vegas Review-Journal.