Clark County Nears Completion of Las Vegas Blvd Phases
Phases C and D of the Las Vegas Boulevard preservation project between Tropicana Avenue and Russell Road are almost finished.
Updated on Nov. 9, 2026 in Casino

Clark County has nearly completed Phases C and D of the Las Vegas Boulevard preservation project, which stretches between Tropicana Avenue and Russell Road. Crews are finishing repaving work through Wednesday, and substantial completion of the phase is set for late January or early February.
Why it matters
The project is upgrading water lines, pedestrian crossings, traffic signals, street lighting, and pavement along one of Las Vegas's most heavily traveled corridors. Clark County plans to begin the final project phases next year, extending the work to the rest of the route.
Phases C and D are budgeted at $60.6 million, part of an estimated $181 million total cost through those phases. The final price of Phase G will not be known until the Clark County Commission approves a contractor and price.
The players
Clark County
Clark County is the Nevada county that encompasses Las Vegas and manages the Las Vegas Boulevard preservation project.
The details
Crews are applying ultra-thin asphalt concrete surfacing on top of dense grade from just south of Tropicana Avenue to the project end before Russell Road, and are removing median island maintenance so smart poles can be installed. The work includes water line replacement, pedestrian crossing improvements, traffic signal upgrades, LED street lighting, and median landscaping, with some landscaping removed to save water and cut costs.
Timeline
Late 2019: Project began with the Sahara Avenue to Spring Mountain Road portion.
June 2025: Phases C and D construction started.
November 1–12, 2026: Ultra-thin asphalt paving completed on Phases C and D.
Late January or early February 2027: Substantial completion of Phases C and D expected.
Seasonal Patterns
The Las Vegas Boulevard preservation project began in late 2019 with the Sahara to Spring Mountain portion and has progressed in phases since. Completing Phases C and D moves the corridor work toward the final phases scheduled for 2028 and 2029.
Drivers along Las Vegas Boulevard will face ongoing lane and median changes through the project's completion in early 2027. Crews will not pave on Tuesday or Wednesday because of the Veterans Day holiday.
The takeaway
Drivers and visitors heading to the Strip should expect continued construction on Las Vegas Boulevard through early 2027, with the corridor's final phases still ahead.
What happens next
Phase G is scheduled to occur between March and October 2028, and Phase H between January 2028 and February 2029, with the Phase G price pending Clark County Commission approval.
Further reading
Learn more about the city's gaming corridor in our Casino coverage.
Source note: This article includes information reported by Las Vegas Review-Journal.