i-80 Gold to Begin Archimedes Mining by Year-End
The Nevada-focused miner reported third-quarter gold output and a net loss while planning start-up at its Eureka County project.
Updated on Nov. 24, 2026 in Business

Live Poll
Do you think new mines benefit the communities near them?
i-80 Gold Corp. produced 11,685 ounces of gold in the third quarter and posted an adjusted net loss of $48.2 million, or 6 cents per share. The company said gold mining at Archimedes in Eureka County is scheduled to begin by the end of 2026.
Why it matters
The start of mining at Archimedes would move i-80 Gold's Nevada operations from development toward production, a key step for a company currently reporting losses. Investors and local stakeholders in Eureka County will be watching whether the timeline holds.
i-80 Gold reported 11,685 ounces of gold produced and an adjusted net loss of $48.2 million, or 6 cents per share, in the third quarter. Projected Archimedes output of 100,000 ounces per year after start-up has not yet been demonstrated in production.
The players
i-80 Gold Corp.
A publicly traded gold mining company that operates projects in Nevada and is developing the Archimedes and Granite Creek properties.
The details
i-80 Gold Corp. completed a feasibility study for the Granite Creek underground project, which has a 9.2 million ton ore reserve. The company is advancing Archimedes through planned mining and processing steps while working with the Nevada Division of Environmental Protection on permits.
Timeline
Q3 2026: i-80 Gold reports 11,685 ounces produced and a $48.2 million adjusted net loss.
End of 2026: Gold mining is scheduled to begin at Archimedes in Eureka County.
Second half of 2027: Full production is expected at the Eureka County project.
Market Landscape
The Archimedes timeline is tied to the Nevada Division of Environmental Protection permitting process, which will determine whether i-80 Gold's Eureka County mine can move from development into production on the schedule the company has announced.
For Nevada residents and shareholders, the timeline means new mining activity in Eureka County is expected within the next year, though the company is still reporting losses. Investors should track the company's quarterly production and permitting updates as the start date approaches.
The takeaway
i-80 Gold's near-term progress depends on turning its planned Archimedes start into steady ounces, so the quarterly production and loss figures are the metrics to watch. Readers following Nevada mining should compare upcoming reports against the stated end-2026 timeline.
What happens next
i-80 Gold is scheduled to begin gold mining at Archimedes by the end of 2026, with full production at the Eureka County project expected in the second half of 2027.
Further reading
Explore more Public Companies coverage for context on how Nevada miners are reporting and planning their projects.
Source note: This article includes information reported by Elko Daily Free Press.