Switch Proposes 510-Megawatt Power Plant in Nevada

The company plans a behind-the-meter facility at the Tahoe Reno Industrial Center to support growing data center needs.

Updated on Oct. 16, 2026 in Data Centers

Switch Proposes 510-Megawatt Power Plant in Nevada

Live Poll

Should local energy regulators prioritize data center expansion over local water usage and environmental concerns?

Switch has proposed a 510-megawatt natural gas power plant at the Tahoe Reno Industrial Center in Northern Nevada. The project, which the company disclosed its ownership of in October 2026, aims to provide electricity to support expanded data center operations.

Why it matters

The facility is designed as a behind-the-meter power generator, allowing Switch to bypass the traditional utility connection queue. This move underscores the significant energy demands required to sustain data center development in the region.

The proposed 20-acre facility utilizes nine gas turbines to generate its 510-megawatt capacity. It is projected to consume 145 acre-feet of water, or 47 million gallons, annually during operation.

The players

Switch

The company is a major data center operator and the primary user and owner of the proposed power plant.

Public Utilities Commission of Nevada

This state regulatory body is responsible for overseeing utility operations and approving energy project filings.

Nexus Fulcrum LLC

This entity filed the initial project proposal with the Public Utilities Commission in June 2026.

NV Energy

The utility provider manages the systemwide power grid and tracks energy demand projections for the state.

Fleet Data Centers

This company received approval for two natural gas power plants from state regulators in September 2026.

The details

Located at the former Sierra Biofuels Refinery, the plant is part of a broader trend of data center operators securing private power sources. NV Energy projects that data centers will increase their share of electricity sales from 5 percent to 64 percent by 2046.

Timeline

  1. The project was initially filed with the Public Utilities Commission in June 2026.

  2. The commission approved two separate natural gas plants in September 2026.

  3. Switch disclosed its ownership of the proposed plant in October 2026.

  4. Construction is planned to begin in the first quarter of 2027.

  5. The plant is scheduled for completion in 2029.

The Tech Race

This development reflects the intensifying competition among tech firms to secure reliable, private energy supplies amid a massive surge in data center power requirements. It signals a move toward decentralized power generation to bypass traditional grid constraints.

The shift toward private power generation by massive data centers may reduce strain on the public grid as demand grows. However, local residents could see increased water consumption by industrial facilities in the Tahoe Reno area.

The takeaway

As data centers account for a larger share of regional energy consumption, companies are increasingly building their own power plants to ensure operational stability. Readers should monitor future regulatory hearings for updates on how this trend impacts local utility rates and resource allocation.

Further reading

Learn more about the infrastructure needs of the industry in the Data Centers section.

Source note: This article includes information reported by Las Vegas Review-Journal.