State Probes Data Center Over 62 Unpermitted Generators

Sen. Michael Testa has asked state regulators for answers after a $1.07 million fine against DataOne's Vineland facility.

Updated on Nov. 10, 2026 in Data Centers

State Probes Data Center Over 62 Unpermitted Generators

Live Poll

Would you support a data center being built in your own town?

The New Jersey Department of Environmental Protection fined DataOne $1.07 million in September for installing and operating 62 natural-gas generators at its Vineland data center without the required permits. State Sen. Michael Testa has now sent a letter to DEP Commissioner Ed Potosnak seeking answers.

Why it matters

New Jersey requires environmental permits for any generator of 37 kilowatts or more, and the violations were identified during a July 29 inspection rather than earlier oversight. The episode adds to scrutiny of data center development in Vineland and surrounding South Jersey communities.

The 62 temporary natural-gas generators are the core technical issue, with New Jersey requiring permits for any unit rated at 37 kilowatts or more. DataOne says the units are temporary until low-emission fuel cells replace them as the site's permanent power source.

The players

Michael Testa

A New Jersey state senator who has taken an active role in questioning state oversight of the Vineland data center project.

New Jersey Department of Environmental Protection

The state agency responsible for enforcing air pollution rules and permit requirements, which issued the $1.07 million fine against DataOne.

The details

DataOne installed and operated the generators without state approvals, a problem the DEP identified during a July 29 inspection after failing to observe them at its previous December 2025 visit. Testa's November 9 letter asks the agency to explain its oversight and enforcement of the facility.

Timeline

  1. December 2025: DEP's last previous site inspection did not observe the generators.

  2. July 29, 2026: DEP inspection identified the generators at the facility.

  3. September 2026: The state fined DataOne $1.07 million.

  4. November 9, 2026: Testa sent a letter to DEP Commissioner Ed Potosnak.

Under the Hood

The case tests how New Jersey's Air Pollution Control Act and its 37-kilowatt generator permit threshold apply to data centers that rely on large temporary power units. Hamilton Township's July moratorium and similar local measures in Galloway, Egg Harbor and Millville show municipalities pursuing stricter controls as data center development expands.

Residents near the Vineland site could face noise and air-quality effects while the generators operate, and the source reports about 1,000 properties affected by noise in a federal complaint. Public concern about facilities of this kind is reflected in polling showing majority opposition to data center development in New Jersey.

The takeaway

Local permitting and inspection gaps can let large industrial equipment run for months before regulators notice, so residents affected by data center projects should track permit filings and inspection records. Both state and municipal decisions shape how these facilities are regulated.

Further reading

Track the broader debate in Data Centers coverage across New Jersey.

Source note: This article includes information reported by Press of Atlantic City.