Army Corps Reevaluates Atlantic Shores Wind Permit

The federal review adds uncertainty to the stalled 2.8-gigawatt offshore wind project off New Jersey's coast.

Updated on Nov. 21, 2026 in Politics

Army Corps Reevaluates Atlantic Shores Wind Permit

Live Poll

Should New Jersey keep pursuing large offshore wind farms along the Jersey Shore?

The U.S. Army Corps of Engineers confirmed Tuesday that it is reevaluating the permit it issued for Atlantic Shores South, a project proposed by EDF Renewables North America to build as many as 200 wind turbines about 9 miles off Atlantic City. The move follows a series of federal setbacks since President Donald Trump returned to office in January 2025.

Why it matters

The Corps permit authorizes the turbines, offshore substations and undersea transmission cables, and the project still needs several other permits. Opponents say the project would harm fishing, marine life and tourism and raise electric bills, while supporters say it would provide fixed-price power, create jobs and reduce New Jersey's reliance on natural gas.

The 2.8-gigawatt project would place up to 200 turbines about 9 miles offshore from Atlantic City, while opponents claim it would cost coastal households $1,158 a year. The Corps has not said how long its reevaluation will take or what conditions it might impose.

The players

U.S. Army Corps of Engineers

The federal agency that issues permits for work in U.S. waters and is now reevaluating its approval of the Atlantic Shores South project.

EDF Renewables North America

The North American arm of the French energy company EDF, which proposed building the Atlantic Shores South wind farm off New Jersey.

Donald Trump

The current President of the United States, whose administration has pursued a series of federal setbacks against offshore wind projects since returning to office in January 2025.

The details

A review could examine the project's effects on the ocean floor, marine habitat, fish and other marine life, and the coastal areas where cables would come ashore. The Trump administration's Environmental Protection Agency pulled back a key air pollution permit in March 2025, and in August a federal judge allowed the Bureau of Ocean Energy Management to reconsider its own approval.

Timeline

  1. January 2025: Trump returned to office and halted new offshore wind approvals.

  2. March 2025: The EPA pulled back a key air pollution permit for the project.

  3. August 2025: A federal judge allowed the Bureau of Ocean Energy Management to reconsider its approval.

  4. November 18, 2026: The Army Corps confirmed it is reevaluating the permit.

Political Context

The reevaluation continues a pattern set by the January 2025 federal halt on new offshore wind approvals, which opponents have cited in arguing for stricter review. Supporters argue that the same federal actions are undercutting New Jersey's clean energy plans, which include the project.

Coastal residents and electric ratepayers in New Jersey could see changes to their power bills and local shoreline depending on whether the project proceeds. The reevaluation means the permits and timeline for construction remain uncertain for now.

The takeaway

Offshore wind projects depend on a chain of federal, state and local approvals, and a delay at any one stage can stall a project entirely. Readers following energy costs in New Jersey should watch whether the Corps' review changes the project's timeline.

Further reading

Explore more reporting in the Government section for context on how federal permitting decisions affect New Jersey.

Source note: This article includes information reported by Shore News Network.