Portal North Bridge Opens to Rail Service

The $1.6 billion two-track span replaces a 116-year-old swing bridge over the Hackensack River in New Jersey.

Updated on Nov. 18, 2026 in Construction

Wide view of a steel two-track rail bridge with fixed arches spanning a tidal river, a commuter train crossing in the distance over marsh grasses.
Regular rail service resumed Sunday on the $1.6 billion Portal North Bridge over the Hackensack River, replacing a 116-year-old swing span. AI Illustration. Upload story photo >

Live Poll

Do you think your local commute is getting more reliable over time?

Regular rail service resumed on the Portal North Bridge on Sunday, and the joint venture of Skanska and Traylor Bros. that built the $1.6 billion project was recognized at a Monday commemoration. The 116-year-old swing bridge over the Hackensack River was retired.

Why it matters

The previous swing bridge frequently got stuck in the open position, causing commuter delays that cascaded throughout the rail corridor. The fixed span is designed to remove that recurring source of disruption for New Jersey rail riders.

The project carried a $1.6 billion price tag and produces a 2.4-mile two-track span that rises 50 feet above the Hackensack River. The timeline for completion against original contract terms was not reported, and the existing bridge remains scheduled for dismantling in 2027.

The players

Skanska

Skanska is a multinational construction and development company headquartered in Sweden that operates major infrastructure projects worldwide.

Traylor Bros.

Traylor Bros. is an American heavy construction and civil engineering contractor known for large bridge and transportation projects.

NJ Transit

NJ Transit is the public agency that operates bus, rail and light rail service across New Jersey.

Amtrak

Amtrak is the national passenger rail corporation of the United States that operates intercity train service along the Northeast Corridor.

The details

Three 400-foot-long, 500-million-pound bridge arches were assembled in Albany and floated about 30 hours down the Hudson and Hackensack Rivers on barges, passing under 18 bridges along the way. The construction team won the NJ Transit contract in October 2021 for the two-track span.

Timeline

  1. October 2021: The Skanska and Traylor Bros. joint venture won the NJ Transit contract for the two-track span.

  2. Sunday, November 15, 2026: Regular rail service resumed on the Portal North Bridge.

  3. Monday, November 16, 2026: Completion of the project was commemorated and Amtrak issued a news release.

  4. 2027: The existing 116-year-old swing bridge is scheduled for dismantling.

Infrastructure Legacy

The retirement of the 116-year-old swing bridge follows decades of Northeast Corridor delays tied to aging movable spans over the Hackensack River. Replacing it with a fixed 50-foot-high span marks a departure from that pattern of repeated openings and stuck bridges.

Commuters on the rail corridor should see fewer delays from stuck bridge openings now that service runs over a fixed span. The project's completion removes a recurring cause of late trains for New Jersey riders who depend on this route.

The takeaway

Long-running infrastructure replacements can remove chronic service disruptions that riders otherwise accept as routine. Following upcoming milestones, such as the 2027 dismantling, shows how the corridor's remaining legacy structures will change.

What happens next

The existing 116-year-old swing bridge is scheduled for dismantling in 2027.

Further reading

For more on large public works, see Construction coverage across the region.

Source note: This article includes information reported by Construction Dive.