New Jersey Finds Unpermitted DataNode Generators
Regulators identified 64 unpermitted power generators at a facility following a July 2026 inspection.
Updated on Oct. 16, 2026 in Data Centers

Live Poll
Should companies be required to obtain environmental permits before installing power infrastructure in your area?
New Jersey regulators found that DataNode operated 64 tractor-trailer-sized power generators without required air permits. The discovery was made during a site inspection conducted in July 2026.
Why it matters
The facility is currently transitioning to permanent fuel cell power, and DataNode maintains that the generator use is a temporary measure. However, the lack of oversight has prompted significant concern from local community members.
DataNode operated a fleet of 64 generators for over 65,000 total hours without permits. The project reached its full fleet capacity in June 2025.
The players
DataNode
This is a technology company that operates data center facilities requiring large-scale power infrastructure.
Cumberland County Department of Health
This local agency is responsible for monitoring public health standards and addressing resident complaints within the county.
The details
Since March 2026, the Cumberland County Department of Health has received more than 100 noise complaints regarding the site's operations. The generators began arriving in July 2024, with operational units scaling up from 16 in October 2024 to the full fleet by mid-2025.
Timeline
July 2024: DataNode generators began arriving at the site.
October 2024: 16 generators began operations.
February 2025: 16 additional generators began operations.
June 2025: All 64 generators were fully operational.
July 2026: Regulators identified the fleet during a site inspection.
The Tech Race
The reliance on temporary diesel power generation highlights the significant energy bottlenecks facing the modern data center industry. This installation reflects a growing friction between rapid digital infrastructure expansion and established regulatory oversight.
Local residents in the area surrounding the site may face ongoing noise disturbances until the facility transitions to permanent power. The regulatory investigation may lead to stricter oversight or mandated operational changes that could affect site power capacity.
The takeaway
Industrial facilities must maintain strict compliance with air quality regulations even when implementing interim power solutions. Residents affected by such operations should continue to document disturbances to ensure their concerns are addressed by local health authorities.
Further reading
For more context on infrastructure regulations, visit Data Centers.
Source note: This article includes information reported by Elko Daily Free Press.