Omaha Reopens Downtown Roads Amid Streetcar Work
The City of Omaha has reopened several downtown streets affected by streetcar construction, with more partial reopenings and utility closures scheduled through early December.
Updated on Nov. 22, 2026 in Industry

The City of Omaha lifted a lane restriction on the Dodge Street Interstate 480 off-ramp and reopened one block of South 10th Street between Farnam and Harney Streets. Additional partial reopenings are scheduled as streetcar-related utility work continues downtown.
Why it matters
Road restrictions tied to streetcar construction have affected traffic patterns across downtown and Midtown Omaha. The staged reopenings and utility closures give drivers and nearby businesses a clearer picture of which routes remain open.
The South 14th Street partial reopening to two-way traffic is scheduled to last until Sunday, Nov. 29. Farnam and Harney Streets between 24th and 20th Streets remain closed into December for utility work tied to the streetcar project.
The players
City of Omaha
The city government of Omaha, Nebraska, which oversees downtown street closures, utility work, and the streetcar construction project.
The details
Harney Street between 10th and 11th Streets reopens Wednesday, and South 14th Street between Douglas and Farnam Streets partially reopens to two-way traffic. Drivers leaving the Farnam Street area between 35th and 36th Streets must turn onto 36th Street, and on-street parking there reopens for local access.
Timeline
Friday, Nov. 20, 2026: Dodge Street I-480 off-ramp lane restriction lifted.
Saturday, Nov. 21, 2026: One block of South 10th Street reopened.
Wednesday, Nov. 25, 2026: South 14th Street and Harney Street partially reopen.
Monday, Nov. 30, 2026: Farnam Street one-block closure from 6 a.m. to 10 a.m.
Early December 2026: Harney Street expected to open to one lane of traffic.
Construction Timeline
The staged reopenings are phases of the Omaha streetcar project, with utility work on Farnam and Harney Streets extending the closure period into December. Downtown drivers are seeing incremental access restored as the work moves block by block.
Drivers heading through downtown and Midtown Omaha should plan around the Farnam Street closure hours and the Farnam and Harney segment closed into December. Local businesses along the affected blocks may see parking and access changes until the phased reopenings are complete.
The takeaway
Downtown Omaha drivers should check the city's closure schedule before traveling, since several streets are reopening in phases through early December. Plan alternate routes for the Farnam and Harney corridors while utility work continues.
What happens next
South 14th Street partial reopening is scheduled to last until Sunday, Nov. 29, and Farnam Street closes for utility work Monday, Nov. 30 from 6 a.m. to 10 a.m.