Deadmans Run Flood Project Starts Phase One
Lincoln officials say the $26 million Deadmans Run Flood Reduction Project has begun construction near the 56th Street detention basin to reduce flood risk in north Lincoln.
Updated on Nov. 17, 2026 in Industry

Live Poll
Do you trust Lincoln's local government to protect your area from flooding?
The Deadmans Run Flood Reduction Project, a $26 million effort to reduce potential flood risks in north Lincoln, has started its first phase of construction near the 56th Street detention basin. Lincoln Transportation and Utilities and the Lower Platte South Natural Resources District provided the update.
Why it matters
The project aims to strengthen Lincoln's stormwater infrastructure and lower flood risk for neighborhoods in the north part of the city. Its multi-year timeline means residents will see construction activity over several seasons before the full benefits are realized.
The project carries a total cost of $26 million, with construction split into phases running through 2030. The source does not provide cost breakdowns by phase or details on how funding is divided between the city and the Natural Resources District.
The players
Lincoln Transportation and Utilities
The city department responsible for transportation infrastructure and utilities services in Lincoln, Nebraska, including stormwater management.
Lower Platte South Natural Resources District
A regional government agency in southeast Nebraska that manages water resources, flood control and conservation across Lancaster County and surrounding areas.
The details
Construction of the first phase has begun near the 56th Street detention basin. Phase two will involve removing certain trees, bushes and weeds near 48th and Francis streets on the University of Nebraska-Lincoln East Campus.
Timeline
Late fall or early winter 2026: second phase construction expected to begin.
End of 2026: first phase expected to be completed.
Spring 2027: second phase expected to be completed.
2030: full project expected to be completed.
Utility Infrastructure Context
The project extends Lincoln's stormwater infrastructure program, which uses detention basins such as the one at 56th Street to hold runoff and reduce flooding in north Lincoln neighborhoods. Its phased, multi-year schedule runs through 2030 and follows the same staged approach to large municipal drainage work.
North Lincoln residents will see construction activity over the coming years as phased work moves through the 56th Street basin and the East Campus area. The project's stated aim is to reduce flood risk in the neighborhoods it serves once construction is finished.
The takeaway
Long-term flood projects like Deadmans Run are built in stages, so residents should expect construction disruption well before the full flood protection arrives around 2030.
What happens next
Second-phase tree removal near 48th and Francis streets is expected to begin in late fall or early winter 2026, with completion of the first phase expected by the end of 2026.
Further reading
Find more coverage of local water and stormwater systems in the Utilities section.
Source note: This article includes information reported by KLKN-TV.