Crews Begin Placing Walls for New Horace Mann
Precast concrete panels are going up for the $45 million replacement of the 1915 Fargo elementary school.
Updated on Nov. 17, 2026 in Education

Live Poll
Do you support your local school district borrowing money for new school buildings?
Construction crews began placing precast concrete walls for the new Horace Mann Elementary School in Fargo on Monday, Nov. 16. The $45 million building replaces the 1915 structure, which was demolished beginning in late June.
Why it matters
The project replaces a century-old school that officials said was difficult to upgrade for safety and lacked space for lunch service and collaborative learning. Fargo families with students in the Horace Mann, Roosevelt and Madison attendance areas will see the new building serve grades K-5 when it opens.
The project is financed through a bond issuance from the district's building fund, with the $45 million total cost covering the new K-5 building. Precast panels weighing up to 52,000 pounds are being placed by crane at 8 to 12 per day, with the full count capped at 140 panels.
The players
Fargo Public Schools
The public school district that owns the Horace Mann site and is financing the replacement building through a bond issuance.
Wysan Precast Services
A Moorhead, Minnesota-based precast concrete company that is placing the large panels at the Fargo site with a crane.
Taracon Precast
A precast concrete manufacturer in rural Hawley, Minnesota, that pours the wall panels in-house before delivery.
The details
Precast concrete walls are poured in-house at Taracon Precast in Hawley, Minnesota, then hauled to the site on semis, where Wysan Precast Services uses a large crane to set them. Since demolition began, the contractor has completed soil improvements and laid footings and foundation.
Timeline
Late June 2026: Demolition of the 1915 Horace Mann building began.
Monday, Nov. 16, 2026: Crews began placing precast concrete walls.
Around Christmas 2026: Precast walls are expected to be fully in position.
End of 2027 or early 2028: Building expected to be completed and turned over to the district.
Fall 2028: New school expected to welcome students.
Season Trajectory
Districts like Fargo facing buildings constructed before 1950 are increasingly weighing demolition against renovation, and Horace Mann follows that pattern by replacing a 1915 structure after citing safety upgrade difficulty and missing lunch and collaborative spaces. The approach reflects a broader decision that aging building stock can cost more to modernize than to rebuild.
Students currently attending grades K-2 at Madison and grades 3-5 at Roosevelt will continue in those buildings until the new Horace Mann opens. Families in the Horace Mann, Roosevelt and Madison attendance areas should expect the consolidated K-5 school to take students beginning in fall 2028.
The takeaway
Replacing an aging school can be a practical route when safety upgrades and space limitations make renovation difficult, and the Horace Mann project shows how that tradeoff plays out in a single district.
What happens next
Crews expect to have the precast walls in position around Christmas, and the district expects the building to be turned over at the end of 2027 or early 2028 ahead of a fall 2028 opening.