Downtown Wilson Construction Winds Down for Season
Crews are shifting to roadway and driveway paving on the Teton BUILD Grant project before winter.
Updated on Nov. 6, 2026 in Construction

Live Poll
Do you support the downtown Wilson road and pathway improvement project?
Construction work in downtown Wilson is nearing the end of the season, with crews moving to roadway and driveway paving. Stormwater and underground utility work on the north side of WY22, a retaining wall north of Edmiston Springs, curb-and-gutter installation and concrete driveway approaches have been completed.
Why it matters
The wind-down marks the close of a summer and fall of construction concentrated on the north side of WY22 in Wilson. Completing north-side improvements before shifting to the south side sets the sequence for the remainder of the project.
Fall construction work is scheduled to conclude within two to three weeks, weather permitting. The source does not provide cost figures or comparator data for the project.
The players
Teton BUILD Grant
The Teton BUILD Grant is the funding program supporting the downtown Wilson construction project.
The details
Traffic cones and barricades will be removed as crews finish. WY22 travel lanes will be repaved to their full width and striped, and unpaved sections of the north-side pathway will receive a graded gravel surface.
Timeline
Next week: remaining concrete work and paving expected to be completed.
Within two to three weeks: fall construction work scheduled to conclude.
April 2027: construction scheduled to resume on the project.
Summer 2027: extended three-lane section scheduled to be completed.
Industry Context
The downtown Wilson project operates under the Teton BUILD Grant, and its north-side-first sequencing sets up the south-side work that follows. The extended three-lane section scheduled for summer 2027 marks the project's next major milestone.
Drivers on WY22 and pedestrians using the north-side pathway should expect traffic cones and barricades to come down as work wraps up. Repaving and striping of the full-width travel lanes will follow as crews finish the season's work.
The takeaway
Downtown Wilson's fall wind-down signals that the north side of WY22 is largely complete before crews turn to the south side. Residents planning around the project can anticipate a pause over winter and resumed work in April 2027.
What happens next
Construction is scheduled to resume in April 2027, and the extended three-lane section of WY22 is slated for completion in summer 2027.
Further reading
Explore more on Construction projects shaping communities like Wilson.
Source note: This article includes information reported by Buckrail - Jackson Hole, news.
Live Poll
Do you support the downtown Wilson road and pathway improvement project?