Silvi Plans Cement Import Terminal at Wilmington Port
North Carolina Ports has signed a 30-year lease with Silvi Materials for a deep-water cement terminal on a 3.9-acre site.
Updated on Nov. 23, 2026 in Industry

Live Poll
Do you expect construction material prices in your area to rise over the next few years?
Silvi Materials announced plans for a deep-water cement import terminal at the Port of Wilmington, supported by a long-term lease agreement executed with North Carolina Ports. The proposed facility would include a 100,000-ton storage dome along with unloading, rail and truck loading equipment.
Why it matters
The project supports Silvi's continued investment in infrastructure needed to serve growing construction materials demand across the Eastern United States. It also reflects North Carolina Ports' commitment to its 2031 Strategic Plan.
The proposed terminal would sit on a 3.9-acre site under a 30-year lease with two 10-year extension options, and include a 100,000-ton storage dome plus two rail and four truck loadouts. The stub does not address whether the project's construction and operations schedule has been secured.
The players
Silvi Materials
Silvi Materials is a Pennsylvania-headquartered construction materials company that has expanded its North Carolina operations through acquisitions and new facilities.
North Carolina Ports
North Carolina Ports is the state agency that operates the Port of Wilmington and the Port of Morehead City.
The details
Silvi plans to receive large ocean-going bulk vessels and distribute cementitious materials to customers by truck and rail. The Wilmington site would have direct access to the CSX rail network, while a similar Morehead City facility would connect to Norfolk Southern.
Timeline
Nov. 1, 2025: Silvi acquired Eagle Rock Concrete.
Late 2027: Operations expected to begin at the Morehead City facility.
Spring 2028: Construction expected to begin at the Wilmington facility.
Fall 2029: Operations expected to begin at the Wilmington facility.
Market Landscape
The terminal extends Silvi's push into bulk cement distribution along the Carolina coast, following the 2025 Eagle Rock Concrete acquisition that expanded its Raleigh-Durham ready-mix footprint. It positions the company to supply the region's construction materials market through both port and inland rail-and-truck channels.
For Wilmington-area residents and businesses, the terminal could change local truck and rail traffic patterns once operational. The stub does not specify effects on consumer prices for construction materials.
The takeaway
Port-based cement terminals show how regional construction supply chains are being rebuilt around deep-water access and rail connectivity. Watch for construction milestones in 2028 to gauge whether the Wilmington timeline holds.
What happens next
Silvi is expected to begin construction on the Wilmington facility in spring 2028, with operations projected for fall 2029.
Further reading
For more on port logistics, see Transportation coverage across the region.
Source note: This article includes information reported by WilmingtonBiz.