UNC Asheville Begins Lipinsky Hall Renovation

The 1964 building will be reshaped into a 475-seat performance hall, classrooms, and new student spaces.

Updated on Nov. 20, 2026 in Lifestyle

Brick mid-century university building with partial renovation scaffolding and a yellow crane against misty blue mountain ridgelines under soft daylight.
UNC Asheville has begun construction on Lipinsky Hall, a 1964 campus building being converted into a 475-seat performance hall, with work set to begin demolition in December 2026. AI Illustration. Upload story photo >

UNC Asheville has begun construction on the renovation of Lipinsky Hall, a building that opened in 1964 and originally served as the university's first student union. Demolition work is scheduled to start in early December 2026.

Why it matters

The project will convert a longtime campus building into a performance venue that will serve as the home of the Blue Ridge Orchestra, expanding space for arts and student life in Asheville. The renovation also brings upgrades to heating, cooling, and lighting in the aging structure.

The renovated building will include a 475-seat performance hall, premier performance halls, classrooms, rehearsal spaces, and upgraded faculty offices. Barringer Construction is the contractor, and the project is funded through state appropriations, UNC System and University trust funds, donations, and grants.

The players

UNC Asheville

The University of North Carolina at Asheville is a public liberal arts university in Asheville, North Carolina, and part of the University of North Carolina System.

Barringer Construction

Barringer Construction is the general contractor overseeing the Lipinsky Hall renovation project.

The details

The renovation adds premier performance halls, classrooms, rehearsal spaces, new student spaces, and upgraded faculty offices, with heating, cooling, and lighting upgrades throughout. Barringer Construction is serving as the project contractor, with funding from the North Carolina General Assembly, the UNC System Board of Governors, and an Office of State Budget and Management Flex Fund award.

Timeline

  1. 1964: Lipinsky Hall is built as UNC Asheville's first student union.

  2. November 2026: Construction on the renovation begins.

  3. Early December 2026: Demolition work takes place.

  4. Spring 2027: A campuswide groundbreaking celebration is planned.

  5. August 2028: Renovations are expected to be completed.

Campus Context

Lipinsky Hall's renovation is funded through the same mix of General Assembly appropriations and UNC System Board of Governors support used for capital projects across the University of North Carolina System. It extends a pattern of converting aging campus buildings into modern academic and arts facilities.

Asheville residents and students can expect construction activity on the UNC Asheville campus beginning in November 2026, with demolition following in early December. Once finished in August 2028, the building will offer a 475-seat venue for the Blue Ridge Orchestra and other performances open to the community.

The takeaway

Renovating older campus buildings like Lipinsky Hall can add performance, teaching, and student space without starting from scratch. Residents interested in the project's progress can follow campus announcements as demolition and groundbreaking milestones approach.

What happens next

Demolition work is scheduled to begin in early December 2026, with a campuswide groundbreaking celebration planned for spring 2027.

Further reading

Explore more Higher Education coverage from across the region.

Source note: This article includes information reported by WLOS.