Council Approves $6.95M I-26 Connector Agreement

The city will reimburse NCDOT for betterments on two sections of the I-26 Connector between Haywood Road and Broadway Street.

Updated on Nov. 11, 2026 in Electric Vehicles

Bold flat-color editorial illustration of a steel truss bridge over a river valley with a curving path and wooded ridgeline behind it.
Asheville City Council unanimously approved a $6.95 million reimbursement agreement with NCDOT on Nov. 10 for I-26 Connector betterments, including greenways and bridge work. AI Illustration. Upload story photo >

Live Poll

Do you support the city spending millions on greenways and bike lanes alongside the I-26 Connector?

Asheville City Council unanimously approved a $6.95 million reimbursement agreement with the N.C. Department of Transportation on Nov. 10 for betterments on the I-26 Connector. The city's contribution covers greenways and bridge decorations outside the scope of the road itself.

Why it matters

The agreement lowers the city's planned spending on betterments from an initial $7.3 million commitment made in 2023, as NCDOT refined cost estimates through negotiations with its contractor. The project is slated to bring major infrastructure improvements to West Asheville and the River Arts District in the coming years.

The city's reimbursement totals $6.95 million, while NCDOT will cover more than $6.5 million of betterment expenses. The current State Transportation Improvement Program estimates total costs of the two sections at over $1.45 billion.

The players

Asheville City Council

The governing body of Asheville, North Carolina, responsible for approving municipal agreements and spending decisions.

N.C. Department of Transportation

The state agency responsible for transportation infrastructure across North Carolina, including the I-26 Connector project.

The details

The agreement covers betterments on two sections of the I-26 Connector running from Haywood Road to Broadway Street, including a West Asheville Greenway connecting Haywood Road to Patton Avenue via an asphalt multiuse path. Bike lanes will be added over the Haywood Road and Bowen bridges, and an 18-foot-wide multiuse path will run down a portion of Patton Avenue.

Timeline

  1. Discussions on the I-26 Connector project began in 1989.

  2. The city made an initial $7.3 million betterments commitment in 2023.

  3. The I-26 Connector Aesthetics Committee disbanded in 2025.

  4. Groundbreaking on the I-26 Connector occurred in April 2026.

  5. Council unanimously approved the $6.95 million agreement on Nov. 10, 2026.

Roadmap

The agreement reflects how the I-26 Connector, a long-debated highway project dating to discussions begun in 1989, is now moving forward with cost-sharing between the city and state. The reduced city contribution from the 2023 commitment signals that cost estimates are being revised as construction proceeds.

Residents who use the I-26 Connector corridor, including drivers and cyclists, will eventually see new greenways, bike lanes, and multiuse paths in West Asheville. The city's reduced betterment spending means the improvements are being delivered with a smaller local financial share than originally planned.

The takeaway

Cost-sharing agreements like this one show how local betterments on state highway projects can shrink as engineering estimates firm up. Residents following the I-26 Connector should watch for updated timelines as construction continues.

Further reading

For more on related local infrastructure, see Electric Vehicles coverage in Asheville.

Source note: This article includes information reported by The Asheville Citizen Times.